填築的 的英文怎麼說

中文拼音 [tiánde]
填築的 英文
fill-up
  • : 動詞1. (墊平或塞滿) fill; stuff 2. (補足; 充滿) replenish; supplement; complement 3. (填寫) fill in; write
  • : 築名詞(貴陽的別稱) another name for guiyang
  • : 4次方是 The fourth power of 2 is direction
  1. On the basis of collecting and arranging a large amount of projects experience, conbined with construction diversion flood passing measures design and hydraulic model test of lihua hydraulic pawer station in 1995 and 1996, the dissertation studies the issues related with characteristics of concrete face rockfill dam including the selection of construction diversion flood passing standard and measures, flood passing during construction period and embankment stage, coffer dam design, construction scheme and general schedule etc. and present preference for project construction

    本文在搜集整理大量工程經驗基礎上,結合蓮花水電站在1995年及1996年導流渡汛工程措施設計及水工模型試驗,對混凝土面板堆石壩導流渡汛標準、導流方式及其選擇、施工期渡汛及壩體分期、圍堰設計以及施工方案及總進度等與混凝土面板堆石壩特點有關問題進行研究,為工程建設提供一定參考。
  2. An example of coal gangue roadbed construction

    煤矸石用於路基填築的探討
  3. In special cases very considerable quantities of waste gypsum from phosphoric acid plants are used to reclaim land after flooding of the sea.

    在特殊情況下,磷酸廠產大量廢石膏用來被海水泛濫過土地。
  4. Proprietary products for permanent reinforced fill sturctures

    永久性加固結構使用物料
  5. Based on the theory of unsaturated soil mechanics and the properties of compacted expansive soil, this paper takes the northern part k12 + 840 - k12 + 920 of nanning urban highway as an example to studies some aspects of lime improvement of expansive soil and the technology of construction. the chief content of this paper is : the lime improvement mechanism of expansive soil ; confirm the technical parameters of lime mixed from the results of test in laboratory ; the scale - down test to define the maximum effective grain size of expansive soil when it is improved by lime ; by building bank slope model and making use of finite element seepage flow program of saturated - unsaturated to calculate the examples, this paper simulates the humidity site in order to checkout the effect of lime improvement ; studies and proves that it is feasible to mix blocky expansive soil and pulverous lime, and to fill roadbed by common construction machines etc.

    本文研究工作就下述幾個方面展開:用石灰改良膨脹土機理;通過室內試驗確定摻灰技術指標;在室內進行膨脹土摻灰最大有效粒徑模擬試驗,即鈣離子水試驗,由此總結出「粉?塊」灰?土攪拌工藝有效性、合理性和可行性;用數值方法對路堤使用期濕度場進行模擬,並與路堤強度?變形計算域耦合,以檢驗土性改良效果,從而探索一種描述改良膨脹土路堤運行工況數值方法;用現有最常用且費用最低施工機具,對灰?土進行「粉?塊」攪拌摻和及路基施工等。
  6. Standard specification for preformed sponge rubber cork and recycled pvc expansion joint fillers for concrete paving and structural construction

    混凝土鋪面和結構建用預制微孔橡膠軟木和可回收pvc膨脹接縫標準規范
  7. Anteklise filling plans for bridge and culvert structures in expressway

    高速公路橋涵構造物臺背方案
  8. Treatment measures for ford earth work of liupan mountain

    六盤山過濕土填築的處置措施
  9. Standard specification for preformed expansion joint filler for concrete paving and structural construction nonextruding and resilient bituminous types

    混凝土鋪面和結構建用預制伸縮縫標準規范
  10. Variance index of the settlements of soft clay subgrade was inducted to analyze the asymmetry settlement rules under the influence of depth of fill, fill speed, geologic types of soft clay etc

    利用這些觀測數據,引入路堤斷面中點和兩側坡腳地基表面3點沉降方差這一統計學指標,詳細分析了地質結構,速率、高度以及硬殼層等因素對軟基不均勻沉降影響,得到了一些有意義結論。
  11. For example the concrete faced rock - fill dam in frigid zone is distinctive in terms of frost resistance and durability, cushion material seepage prevention and frost heave, adaptability of darn filling with season coordination among construction diversion, flood discharge and the whole construction schedule etc. lianhua construction which is situated in mudanjiang basin of heilongjiang province firstly creates the successful record of construction of large - size faced rock - fill dam in frigid zone, a series of internal and external problems not having a precedent to go by have been solved

    如在面板抗凍耐久性、墊層材料防滲和凍脹特性、壩體與季節適應性、導流和度汛與總體進度協調等方面,寒冷地區混凝土面板堆石壩均有其獨特之處。蓮花工程位於黑龍江省牡丹江流域,首創了高寒地區修建大型面板堆石壩成功記錄,解決了一系列國內外均無先例難題。
  12. In the simulation and analysis on culvert construction, the method of foundation - pit excavation layer by layer and step by step was used, i. e. the method that makes the surface of excavation have no stress, when the elements were excavated gradually in period of construction. at this process, the state of soil is unloading, the laws of stress field and displacement field with the depth of excavation were studied. based on the obtained stress field and displacement field after the excavation was completed, by using of the newly increased filling - elements " gravity and the grinding force, the simulation of the construction of body of the culvert and foundation - pit ' s filling layer by layer had also been done in this dissertation

    用有限元法模擬分析涵洞基坑開挖時,採用分層、分步模擬開挖過程方法,即將計算域內單元分層「挖去」 ,使開挖表面成為無應力表面方法,分析土體在卸載狀態時應力場和位移場隨開挖深度變化規律;在洞體施工后,回土體時,據開挖完成時應力場、位移場,通過逐級增加計算域內單元數目,施加每級新增加單元自重荷載,利用有限元法模擬基坑及上覆土體分層填築的施工過程,這不僅反映土體處于再加載應力狀態時,土受力及變形一般規律,而且這種將地基? ?涵洞? ?土體作為一個統一整體進行模擬方法,量化了三者之間相互作用關系。
  13. Based on the feature of subgrade construction and with the analysis of the observed settlement data, a series of stress - strain isochrones are arranged in this paper

    本文基於高速公路路基填築的特點,通過實測沉降資料分析,整理出一系列應力應變等時曲線。
  14. So far as the mixing material for building the earth - rock fill dam with clay core for shiquanhe hydropower station is concerned, the effect from the variation of the sand content for the filter material on the maximum dry density and the relevant parameters are to be determined within the variation area of the mixing mass ratio of ( 46 ~ 54 ) : ( 54 ~ 46 ) through this experiment, due to the max, dry density is largely influenced by the mixing ratio of both the lifter material and the clay and the sand content of the filter material, so as to determine the actual filling compactness of the mixing material of the core

    摘要由於獅泉河水電站粘土心墻土石壩摻合料最大幹密度受反濾料與粘土料摻合比例、反濾料含砂率影響較大,因此擬通過本試驗確定摻合質量比在( 46 ~ 54 ) : ( 54 ~ 46 )范圍變化時,反濾料含砂量變化對最大幹密度影響程度及相關參數,從而確定心墻摻合料填築的實際壓實度。
  15. Using the finite element method ( fem ), the simulation and analysis on this construction process were carried on, and the different stress state of soil at different construction period was rendered. and the influence of different stress paths ( foundation excavation - unloading & excavation filling - reloading ) on the stress and the displacement was also reflected and researched. the law of non - linear constitutes of soil was presented in the simulation and analysis

    模擬分析再現了土體非線性本構關系,得到了基坑開挖時土體變形和應力變化一般規律;在基坑及上覆土體回時,通過分層填築的有限元模擬和地基、涵洞、土體三者相互作用有限元分析,得到施工結束太原理工大學碩士學位論文時位移場和應力場,同時求得涵洞結構內力。
  16. Abstract : in the filling construction of lianhua concrete face rockfill dam, we have paid attention to plan the material sources according to the actual conditions, such as, using the excavated materials in other structures in order to reduce the cost, adopting the measures of filling by zones to quicken the construction progress and solve the construction problems during the cold seasons, using the convenient transportation roads to the dam and good road surface quality to ensure the high intensity filling, and selecting the rational construction equipment to make full use of the all equipment

    文摘:蓮花面板堆石壩施工中,注意對壩料源做出符合工程實際情況規劃:利用其他建開挖料降低造價;採用分區填築的措施,加快施工進度和解決寒冷季節施工問題;方便上壩交通道路網和良好路面,為高強度提供有力保證;選擇合理配套施工設備使設備得到優化利用。
  17. Compaction degree is the key index to control construction of embankment

    摘要壓實系數是控制路堤填築的關鍵性指標。
  18. 1. on the bases of some basic suppositions, terzaghi ' s one dimensional consolidation and principles of layered summation method, the paper draw the formula which can calculate the embankment of layered filling and take the formula into programme ; 2. building the finite difference model of layered high - stack soil, carrying out numerical simulation of construction sequence, construction velocity, interface element of layer - stacked, the author get the numerical solution

    1利用一些基本假定,根據太沙基一維固結理論和分層總和法基本原理,推導出來計算分層體自身沉降公式,並編制了程序; 2建立了分層方路堤問題有限差分模型,並對分層填築的施工順序、施工速度,界面單元進行了數值模擬,獲得了位移場和應力場數值解。
  19. Maritime structures - code of practice for dredging and land reclamation

    海工建物.疏浚和土地填築的實施規程
  20. Simultaneously, the quality control method for the compaction, the construction technologies and measures and the roller - compacted parameters are studied and optimized, in this way the investment is saved at last

    同時,制訂了壓實質量控制方法,研究和改進了填築的施工工藝和措施,優化了大壩體型及施工碾壓參數,節約了投資。
分享友人