水底工程 的英文怎麼說

中文拼音 [shuǐdegōngchéng]
水底工程 英文
submarine work
  • : 名詞1 (由兩個氫原子和一個氧原子結合而成的液體) water 2 (河流) river 3 (指江、河、湖、海、洋...
  • : 底助詞(用在定語后, 表示定語和中心詞之間是領屬關系, 現在多寫作「的」)
  • : Ⅰ名詞1 (工人和工人階級) worker; workman; the working class 2 (工作; 生產勞動) work; labour 3 ...
  • : 名詞1 (規章; 法式) rule; regulation 2 (進度; 程序) order; procedure 3 (路途; 一段路) journe...
  1. Drainage way with floor blocked up, drainage with back outlet sanitary facilities and drainage with floor descended are discussed and summarized. a new drainage way with floor descended is introduced which solves the problem of seeper drainage

    實例中,提出了一種新的下沉式排方式,徹解決了目前下沉式作法的下沉空間積排除問題。
  2. In order to detect the bottom thickness, cavity, leak and deformation of steel meshes in secondary lining of concrete in tunnel construction, the authors evaluate the wave character and the detected result in the second lining of the tunnel using surveying radar technology and conclude the wave character in the tunnel lining which has mass defect and tested the accuracy and reliability of this technique

    摘要為檢明隧道混凝土二次襯砌中的界厚度、空洞、漏、鋼筋網變形等質量問題,利用探地雷達技術,通過對檢測方法及檢測實驗的研究,進行隧道二次襯砌中雷達波形特徵參數及檢測結果評價,總結了隧道襯砌質量問題的雷達波形特徵,驗證檢測方法的精度和可靠性。
  3. Using norm method to prepare the construction bidding pretender for hydraulic project

    定額法編制招標標
  4. Using the opened thermosiphon of 38x3 as experimental element and water as working fluid, the characteristics of dynamic low load boiling, stable severe boiling heat transfer coefficient and critical heat flux are gotten for the opened thermosiphon at the pressure of 0. 02 - 0. 1mpa and 0. 1 - 0. 8mpa respectively, which makes up the drawback that the opened thermisiphon has not yet accurate boiling heat transfer relationship formulas. by means of experimental results, an opened thermisiphon waste heat recovery boiler is designed for the high temperature gases that the positi e electrode copper refining furnace exhaust, which overcomes effectively the drawback of short life, little capacity and unable to inspect that the closed steel - water thermosion has

    本文以上常用的38 3的開口封為實驗元件,以質,對開啟式熱管內的動態低負荷沸騰、穩態旺盛沸騰及臨界沸騰特性進行系統的可視化實驗研究,實驗壓力為0 . 02 0 . 8mpa ,實驗得出了38 3的開口封管在作壓力為0 . 02 0 . 8mpa和0 . 1 0 . 8mpa下的管內沸騰傳熱系數及臨界熱負荷計算關聯式,彌補了開口封管? ?這一新型傳熱元件尚無準確的沸騰換熱關聯式的缺陷。
  5. What ' s more, we put forward some experienced formulas on the basis of the cortical analysis. the result of the research show that by installing diffluent piers with low ridge, we can eliminate the root of oscillatiny water jump, perfect the energy dissipation effect of water jump, also, we can improve the flow condition of down - stream. the fact that the main flow of down - stream is in the middle, not only effectively lower the speed of the bottom flow in the ridge rear, alleviate the erosion to the river bed, but also avoid the heavy wave resulted from the main flow in the surface, thus improve the surface wave of down - stream obviously. we can work out the body style parameters of diffluent piers with low ridge according to the project flow condition and experience formulas, and then reckon the down - stream surface wave condition for the protected building of the down - stream bank

    研究結果表明:設置低坎分流墩后,消除了擺動舌擺動的根源,提高了躍的消能效果,改善了下游流流態。下游體的主流在中部,既有效的降低了坎后流速,減輕流對河床的沖刷,又避免了主流位於表面導致波浪過大的結果,下游的面波浪明顯得到削減。依據經驗公式,可根據流條件設計出低坎分流墩的體型參數,進而估算出下游沿面波浪,為下游岸邊的砌護提供依據。
  6. Then the article analyses the effecting elements about the economic result of blasting and puts forward some improving measures, and summarizes optimizing model on economic result of blasting both internal and overseas bearing upon. the theory is based on the blasting cost model, which proposed by dr. zhong hanrong. combining with the specialties of water and electricity engineering, starting off through blasting result, it emphasizing considers drilling cost, deep hole bench blasting cost, reblasting cost, and the cost of bottom fleet hole blasting that in mixed loading emulsion explosive blasting

    本文在加拿大鐘漢榮博士提出的爆破成本模型基礎上,結合的特點,從爆破效果出發,著重考慮了應用混裝乳化炸藥爆破的鉆孔成本、深孔梯段爆破成本、二次爆破成本和爆破后根淺孔爆破成本,以塊度、振動、安全為約束條件,以這四項成本最小為目標函數,廣泛收集各種爆破經濟技術條件,建立了爆破優化經濟數學模型。
  7. Taking bench shooting of the shuibuya yihongbao project as example, it makes use of the digital television system of drilling overall - hole wall to actually measure, the testing result of lateral fractural range is 4 - 5m, and that of bottom fractural range is about 3m

    本文試驗作是以布埡溢洪道梯段爆破為實例,採用鉆孔全孔壁數字電視系統對混裝乳化炸藥爆破破裂范圍進行了實際測試,測試結果為:側向破裂范圍為4 5m ,部破裂范圍值為3m 。
  8. Since 1976 it has been made great achievements which has conducted water more than 100 billion m3 and has been an important project of heilongjiang province. but recently the channel has been seriously freezing - melting eroded and sand of cliff edge has been deposited along the channel, which resulted to highten the channel bottom, increase width of the channel and reduce horse road. what all above have affected to apply safely channel so it is necessary to repair comprehensive

    自1976年建成以來,已累計引100多億立方米,取得了巨大的經濟效益,成為黑龍江省西部關繫到國計民生的重點,但近年來渠道破壞嚴重,凍融侵蝕強烈,邊壁剝蝕下來的泥沙經渠道內流搬運沿發生淤積,導致渠抬高,渠寬增加,馬道縮小,已經嚴重影響到渠道的安全運用,必須進行綜合治理。
  9. The incident wave height h1 / 3 is in the range from 0. 1m to 0. 25m, and the peak period tp in the range from 1. 0s to 2. 0s. the ratio of s / h1 / 3, which refers to the subface level of wharf deck ( s ) to the incident wave height ( h1 / 3 ), is between - 0. 1 and 0. 7. three different shore connecting types : open - piled, permeable slope with armored 1ayer of dolosse b locks and impermeable slope with armored layer of concrete plate, are set in the experiment for the research on the effects of boundary condition with different shore connecting types on the wave impact

    本文的物理模型試驗在大連理大學海岸和近海國家重點實驗室的大波流槽中進行,試驗中選用的隨機波靶譜為改進的jonswap譜,入射波波高h _ ( 1 / 3 )范圍為0 . 1m 0 . 25m ,譜峰周期t _ p范圍為1 . 0s 2 . 0s ,碼頭面板的相對凈空(碼頭面板面距離靜面的距離s與入射波波高h _ ( 1 / 3 )的比值)范圍為- 0 . 1 0 . 7 ,其中s / h _ ( 1 / 3 )為負值時表示碼頭面板面位於靜面以下。
  10. A brief introduction is given to the treatment of the zeya dam foundation, principles of seepage control and design of the concrete face rockfill dam of the zeya reservoir. as for the excavation of the sand - gravel zones, except the toe slab and its 1 / 9 bottom width down stream, the alluvial layers are excavated to the micro - weathered rocks, while the other sections remain unexcavated. regarding to the treatment of the fracture zones, concrete filling is used for the toe slabs and semi - permeable materials are used for other section. according to the construction characteristics, a filter is placed in the down stream embankment foot. to improve the integrity of the dam foundation and anti - seepage capability consolidation grouting and curtain grouting are adopted. as a result safety, economic benefit, convenience in construction and good performace are achieved

    簡要論述澤雅庫面板堆石壩壩基處理和防滲的原則及設計要點.趾板基礎和堆石體各區砂礫石基礎開挖,除趾板與其下游1 / 9寬范圍以及壩腳挖除沖積層至弱風化(局部微風化)基巖外,其餘部分均予以保留.斷層破碎帶處理,趾板部位採用混凝土塞,其它部位採用半透料置換,並根據本特點在下游壩腳加設了反濾層.為提高壩基的整體性和防滲性能,對趾板進行了固結和帷幕灌漿.達到了安全、經濟、便於施的目的,運行情況良好,可為面板堆石壩的設計和研究提供參考與借鑒
  11. The phenomenon of crack that appears in the hydraulic culvert and sluice is explained separately. the rule is concluded. the mechanism that forms the crack is studied

    涵閘墩墻和板混凝土的裂縫現象分別進行了闡述,總結其規律,分析其成因,並研究其開裂機理,為採取相應的防裂措施提供理論依據。
  12. Work started on 14 january 1935 and was completed on 22 march the same year, in all just 56 working days. the work to connect the submarine pipeline with the land mains on the island and in kowloon, was completed on 9 april

    於1935年1月14日展開,同年3月22日完成,共需56個作天,連接九港兩地海沉管與地面,則於4月9日完成。
  13. The proposed landing point at the corner of the typhoon shelter is the only option according to the findings of the preliminary project feasibility study report for the project " laying of western cross harbour mains and associated land mains from west kowloon to sai ying pun "

    根據敷設由西九龍至西營盤的西區海管和相關陸上輸可行性初步研究的結果,位於避風塘一角的擬議陸點是唯一的選址。
  14. Making water works preliminary budget, its framework and norm. 2 ) making and auditing regulations for tendering of water works. 3 ) auditing water works budget

    利基本建設概算編制規定及定額修編; 2 ) 、估算、概算、預算、標的編制及審核; 3 ) 、審計。
  15. Led underwater light is now widely used as the decoration lighting in fountain of park, pool of walking street, music fountain of residence zone, brook, water project of plaza, swimming pool of villa, aquarium and so on

    Led燈目前廣泛應用於公園噴泉、步行街池、小區音樂噴泉、花園小溪、廣場、別墅游泳池、家庭族館等裝飾照明效果。
  16. The retaining wall reclining on the slight slope built on soft foundation is usually used in protecting the shore of river, the contradiction between the lack of impartiality in stress of the base and the small stress allowed by the foundation as well as the lack of stabilization of the breast wall is a hard nut to crack in the engineering. in the paper, a tenon - base is added under the base of the retaining wall, on the study of the choice of the parameters and formulas used in calculation and the research of theory used in calculation, method used to deal with the load, etc, the writer gives a way to crack the nut mentioned above paragraphs and presents a qualitative and quantitative analysis about them, such as the equivalent inner friction - angle ( d ) and the passive press of the clay ( ep ), etc. in the end of the paper, using modern optimization method, a design of the retaining wall reclining on the slight slope built on soft foundation is done, the result is economical, and accords with the fact

    軟基上的仰斜式擋土墻在河道護岸中經常遇到,仰斜式擋土墻基偏心應力較大和軟基土地基容許承載力偏小的矛盾以及擋土墻抗滑穩定不足是中難以解決的難題。本文在對仰斜式擋土墻設計中有關計算參數的選擇、公式的選用應該注意的問題進行了研究,對河道護岸軟基礎上的仰斜式擋土墻採用凸榫基礎處理的方法,就其計算理論、設計驗算中各荷載的具體處理方法進行了較為細致的研究,提出了解決軟基礎上的仰斜式擋土墻難以解決的難題的方法,並對有情況下粘土等效內摩擦角_ d 、凸榫被動土壓力e _ p等在計算中的取值提出了定性和定量的分析。最後利用現代優化方法對軟基礎上的仰斜式擋土墻進行了結構優化設計,得出了符合實際的結果,與其它重力式擋土墻形式進行比較,取得了明顯的經濟效益。
  17. According to the documentation collected from domestic and abroad wang wei dong who works in huadong architect and structure institute utilizes the similar work property between the underground continuous wall and pile subjected the vertical loads, and introduces poulos method of elasticity and plastic which applies to pile foundation into the calculation for subsidence of underground continuous wall. pujialiu and yu yuzhou from water and electronic engineering of qinghua university, according to the result of three axes, define the concrete parameter utilize the model of non - linear e - b combined with the design cross section of dam in xiaolangdi, yellow river accept the total stress programme of thepd dam, and we analyze the stress and displacement of plastic concrete diaphragm wall by finite element method in comparison with the result of common concrete one. at same time, we consider the effect of the character of plastic concrete diaphragm wall which is composed of different gradients and adopting the level of stress and pulling stress infers whether the plastic concrete diaphragm wall is safe or not

    地下連續墻是一種歷史較短的施方法,目前,砼防滲墻的設計還是以傳統的設計方法為主,根據查找國內外文獻資料,華東建築設計院王衛東利用地下連續墻與樁在豎向荷載作用下的作性能有相似性,將適用於樁基的poulos彈性理論引入對地下連續墻的沉降計算中;清華大學系濮家騮、于玉貞根據三軸試驗結果確定混凝土的參數,利用非線性e - b模型,結合黃河小浪土石壩設計剖面,採用thepd土石壩總應力序,對深覆蓋層塑性混凝土防滲墻的應力、位移進行有限元分析,並與普通混凝土防滲墻計算結果加以對比,同時分析了不同配比塑性混凝土特性的影響,並採用應力平和拉應力數值來判斷塑性混凝土防滲墻的安全度。
  18. With the widespread implementation of the tender offer and tender bidding system in the water conservancy and hydroelectricity engineering ( wche ), the cost of projects shall be estimated in time by the design unit and the contractor in order to work out the tender and the quoteprice

    普遍實行招投標制度,這就要求設計單位和承包商及時測算出造價,以便於編制標和報價。因此,造價系統的研製與開發是一項具有重要意義的作,同時也是一項非常艱難的作。
  19. China ' s trans - century super large water conservancy project - the xiao langdi water conservancy project on yellow river was completed in 2001

    中國跨世紀的特大型黃河小浪利樞紐已於2001年度全部竣
  20. The xiaolangdi multipurpose project on the yellow river is one of the most changeable and large - sized projects in the world, which is generally considered by the experts at home and abroad, because of its important strategic position, peculiar general layout, complex geological conditions, strict operation required, huge scale, high technical requirements and construction difficulty

    黃河小浪利樞紐戰略地位重要,樞紐布置獨特,地質條件復雜,沙條件特殊,運行要求嚴格,規模巨大,技術要求高,施難度大,是國內外專家公認的世界上最具挑戰性的大型之一。
分享友人