fs finish-to-start 中文意思是什麼
fs finish-to-start
解釋
完成到開始關系-
Finish - to - start ( fs ) is the task link most frequently used. start - to - finish ( sf ) is seldom used
完成-開始( fs )鏈接是最常使用的鏈接類型,而開始-完成( sf )鏈接類型則很少使用。 -
* * * * for example, if it ' s a finish - to - start ( fs ) link, the task begins as soon as its predecessor finishes
譬如,如果是完成-開始( fs )鏈接,則任務的開始日期為其前置任務的完成日期;如果是開始-開始( ss )鏈接,則任務的開始日期為其前置任務的開始日期。 -
Most likely, you ' ve linked many of your tasks with a finish - to - start ( fs ) link, so that the successor task does n ' t start until its predecessor task finishes
很可能您已使用完成-開始( fs )關系鏈接了很多任務,因此後續任務要等其前置任務結束后才能開始。 -
Tasks linked with a finish - to - start ( fs ) link add more time to a project ' s duration than tasks linked either with start - to - start ( ss ) or finish - to - finish ( ff ) links
使用完成-開始( fs )鏈接的任務要比使用開始-開始( ss )鏈接或完成-完成( ff )鏈接的任務使項目工期增加的時間多。 -
There are four kinds of task dependencies in microsoft project : finish - to - start ( fs ), in which a task cannot start until another task finishes ; start - to - start ( ss ), in which a task cannot start until another task starts ; finish - to - finish ( ff ), in which a task cannot finish until another task finishes ; and start - to - finish ( sf ), in which a task cannot finish until another task starts
在microsoftproject中,有四種類型的任務相關性:完成-開始( fs ) ,在此類型中,某一任務完成後,另一項任務才能開始;開始-開始( ss ) ,在此類型中,某一任務開始后,才能開始另一項任務;完成-完成( ff ) ,在此類型中,某一任務完成後,才能完成另一項任務;開始-完成( sf ) ,在此類型中,某一任務開始后,才能完成另一項任務。
分享友人