墩基礎 的英文怎麼說

中文拼音 [dūnchǔ]
墩基礎 英文
pier foundation
  • : Ⅰ名詞1. (土堆) mound 2. (墩子) a block of stone or wood Ⅱ量詞(用於叢生的或幾棵合在一起的植物) cluster
  • : 名詞(墊在房屋柱子底下的石頭) plinth
  1. We look for the optimum alternative on the basis of analyzing the internal connection of the diffluent piers body style parameters and the wave

    在分析分流體型參數與波浪間的內在聯系的上,尋找較優的分流方案,並在理論分析的上提出一些經驗公式。
  2. The superstructure of the bridge is a three - span ( 80m + 130m + 80m ) continuous rigid frame. the main piers are single - column flexible solid piers, whose foundation are 2. 0m dug piles. the abutments are light - type box abutments, whose foundation are 1. 2m bored cast - in - place piles

    該橋上部為80m + 130m + 80m三跨連續剛構;主為單柱柔性實體,其為2 . 0m挖孔樁;橋臺為輕型箱式橋臺,其為1 . 2m鉆孔樁。
  3. Based on the stochastic finite element method, the reliability of the arch dam gravity abutment is analyzed, and the corresponding reliability index is calculated

    然後在隨機有限元的上進行拱壩的拱座? ?重力的強度和抗滑穩定可靠度分析,計算相應的可靠指標。
  4. Usually, it is accustomed to name the bridge stride as the substructure of bridge

    通常習慣稱橋跨為橋梁的上部結構;稱橋,橋臺及其為橋梁的下部結構。
  5. In which, it gives inquiring of the construction of deep - water foundations and the usage of floating crane. the construction program of bridge pier foundation will be fixed according to the water depth. if the water depth is less than 4m, pier foundation will adopt the method of building island by earth filling ; if the water depth is more than 4m and there is over burden at river bed, at the same time, it has sufficient bearing capacity to load steel pipe pile, the steel pipe pile platform will be adopted

    其中,對深水的施工及浮吊的使用進行了探討,根據水深確定橋墩基礎的施工方法,對水深不超過四米的橋墩基礎,採用填土築島的方法:對水深大於四米,河床有覆蓋層,且能保證鋼管樁具有足夠的承載力的橋,採用鋼管樁平臺;對主河道上河床沒有覆蓋層,鋼管樁無法插打的橋,採用浮式平臺。
  6. Based on the urgent need that pier protective device primarily designed needed to be tested its crashworthiness by the impact of ship in multi - situation, etc in multi - angle and multi - water, the writer analyzed the critical elements that affect the simulation of the collision between ship and pier protective device, and found the feasible way to deal with the conflict between calculation efficiency and precision. using this method and employing ansys / ls - dyna program, which is the universal nonlinear dynamic analysis software, a head - on collision between ship and pier protective device designed for guanzhou river bridge is simulated and presented, the simulation of time history course of full - scale mini - collision between ship and pier protective device was taken into reality with a spot of elements ( less than 21000 ) and scanty time ( 9 hours on p4 pc )

    本文在前人研究的之上,結合船橋碰撞實例,對碰撞計算機模擬模擬的關鍵技術進行了研究,在效率與精度的矛盾中找到平衡,對一艘2000噸級散貨船橫橋向正撞廣東管洲河大橋橋防撞鋼套箱這一種工況進行了計算機模擬模擬,實現了以較小的單元和較短的時間模擬碰撞的時間歷程,模擬滿足工程精度要求,解決了目前碰撞模擬計算周期太長的問題,同時模擬模擬得到的結論對該類防撞裝置提供了有價值的參考。
  7. This may be due to the settlement of foundations or to a differential temperature movement of supporting piers.

    這種運動可以是由於沉降或由於支因不同溫度變化而產生。
  8. Summarizing the conclusions of computation in available literatures and analyzing synthetically actual experimental data, the paper established an interaction model of beam and rail, and by adopting fem and a program compiled by c + + language, this paper studied and calculated the rupture forces in the continuously welded rails ( cwr ) on a specially - designed simply - supported reinforced concrete bridge, and the distribution of rupture forces in rails as well as the law of their transmission to bridge piers and abutments

    摘要在總結已有文獻計算結論的上,綜合分析實際測試數據,建立橋上無縫線路梁軌相互作用的力學模型,採用有限元方法和c + +語言編程,研究、計算特殊設計的混凝土簡支梁橋上無縫線路鋼軌斷軌力的分佈及其對橋梁臺的傳遞規律。
  9. The new construction technique applied to the huge steel boxed cofferdam for foundation of pylon pier no. 2 of wuhan tianxingzhou changjiang river rail - cum - road bridge was to fabricate the cofferdam in integrity in workshop, shift it down to river and float it to the pier site where it is then accurately positioned by pre - tensioning at the anchor pier

    摘要武漢天興洲公鐵兩用長江大橋2號主塔墩基礎大型鋼吊箱圍堰採用工廠整體製造,下河浮運至位,利用錨施加預拉力精確定位的施工新工藝。
  10. Works are accomplished as follows in this paper : firstly, according to the real condition of the fourth pier, through analysis of several generally - used anti - slipping schemes, new method has been put forward to substitute anchored column pile with the foundation of drilled shafts so as to prevent cofferdam from slipping

    為此本文主要做了以下工作:首先根據4 #墩基礎的具體條件,通過對現有常用的幾種抗滑方案的綜合比較分析,提出了以工程本身的鉆孔樁代替錨固柱樁防止鋼圍堰滑移的方案。
  11. Blasting removal for anchorage block foundation behind penstock of tgp power source station

    三峽電源電站引水鋼管壩后鎮墩基礎拆除爆破
  12. Pile group effect of main pylon foundation of sutong bridge

    蘇通大橋主塔墩基礎群樁效應研究
  13. A finite element numerical model for arch dam - gravity pier - foundation system was established to evaluate the effect of high gravity piers on the stress, deformation and anti - sliding stability of sizhai arch dam, taking the following factors into account, such as the possible elastoplastic deformation of foundation rocks and the nonlinear interaction between the interfaces of gravity pier - dam foundation, the joint surfaces beneath the right bank, and the interfaces of arch dam - gravity pier

    摘要為評價高重力對四寨拱壩的應力變形和抗滑安全的影響,建立了拱壩重力系統的有限元數值模型,其中考慮重力墩基礎、右岸夾層和拱壩重力等交界面的非線性相互作用,以及巖材料的彈塑性變形行為。
  14. Belled pier foundation

    鉆孔墩基礎
  15. Analysis of anti - washing construction of fourth main tower pier of great sutong bridge

    蘇通大橋4號主塔墩基礎防沖刷施工難點分析
  16. Discussion on design and structure of pier foundation

    墩基礎設計及構造探討
  17. According to features of diffcult anti - washing construction of pier foundation under compley hydroraphic, gological, and water potential conditions, combining construction condition methods, author analyze and conclude key points and difficulties of anti - washing construction of the fourth main pier of great sutong bridge, and difficulties in construction and relevant countermeasures

    摘要針對在復雜的水文、地質、河勢條件下進行橋墩基礎沖刷防護施工難度大的特點,結合施工工藝和方法,對蘇通大橋主橋4號主塔沖刷防護施工中的重點難點、施工中出現的不利隋況及應對措施進行了分析研究。
  18. With reference to the hydrologic data and geologic conditions of the changjiang river over the years, this paper analyzes the features of and key technical problems to be resolved in the construction of in - water pier foundations in the north river branch of tianxingzhou changjiang river bridge. accounts for the construction organization principle preparation and construction implementation of the foundations, comparison and selection of working platform and steel cofferdam to be used at each pier site, and also summarizes the construction methods for the deep water steel cofferdams of the bridge

    摘要根據長江歷年水文資料、地質情況,分析了天興洲長江大橋北汊水中墩基礎施工的工程特點和要解決的關鍵技術,介紹了施工組織的原則制定和實施過程、各位平臺及圍堰的方案比選,總結了該橋深水鋼圍堰的施工方法。
  19. Its main span, which is 60m long, is made up of prestressed concrete continuous beam. the fourth pier, one of the main piers, adopts the compound foundation constituted with double - siding steel cofferdam and drilled shafts which stands on the deep - water and slopping river bed where geological condition is very complex, so the cofferdam has the trend of slippage

    渝懷鐵路第20標段阿蓬江大橋全長343 . 06m ,主跨為60m的預應力混凝土連續梁, 4 #是其一個主採用雙壁鋼圍堰與鉆孔樁相結合的復合
  20. Based on the model simulation test of the pile foundation of xiabaishi bridge in fujian province, the effect on the rock limit bearing capacity is analyzed through elastic modulus variation of the bridge pile

    摘要依據福建省寧德地區高速公路下白石大橋主橋墩基礎模型模擬試驗,分析了橋彈性模量變化對巖極限承載力的影響。
分享友人