拔樁機 的英文怎麼說

中文拼音 [zhuāng]
拔樁機 英文
extraction jack
  • : Ⅰ動詞1 (拉出; 抽出) pluck; pull out; pull up; draw; move 2 (吸出) draw; suck out 3 (選取 提...
  • : Ⅰ名詞(樁子) pile; pole; stake Ⅱ量詞(用於事情)
  • : machineengine
  • 拔樁 : pile pulling; pile extracting拔樁機 pile-drawer; pulling machine
  1. Study on uplift mechanism and calculation of dx pile

    承載理及設計計算方法研究
  2. If there is no over burden at the river bed, the steel pipe pile cannot be inserted, the floating platform will be adopted, during overwater construction, the author ( using zhong - 60 floating box, etc. ) assembled 40t floating crane by his own design, in this way, the floating crane completed the work of overwater transporting and lifting, such as the transporting of s teel pipe pile, inserting, the erecting of overwater construction platform, overwater moving of drill grid crane, lifting of lifting box of cushion cap, pulling out of steel pipe pile

    在水上作業中,作者利用中- 60浮箱等設備自行設計、拼制了40t浮吊,完成了水上運輸、水上起重等作業,如鋼管的運輸、插打、水上施工平臺的搭設、鉆吊車的水上轉移、承臺吊箱的起吊、鋼管除等作業。
  3. Vibratory pile driving and extracting equipment - safety operation rules

    振動沉拔樁機安全操作規程
  4. The wire rope laying mechanism design of the lifting system of the vibrating drawing pipe pile engine

    管式打提升系統排繩構設計
  5. In this paper, based on the static - load tests of tension piles in soft ground lying on the province of zhejiang such as zhongshan garden, gongchen bridge canal piazza, etc, the calculations of ascending displacement, developing mechanism of the side friction and utmost bearing capacity of the tension piles are studied

    本文以中山花園、拱宸橋運河廣場等浙江軟土地區抗靜載試驗為背景,對抗承載力計算、上量計算、抗側阻發展理進行了分析研究。
  6. The mechanism of reinforcing steel bar under the press or pull is researched and the characteristics under the pull - press cyclic loading is studied in composite foundation. it shows that the stress concentrating on the reinforcing steel bar and the increasing stress can be seen with the increasing of cyclic times. residual strain always exists after unloading without considering the size of pullout force and increases slowly with the cyclic times

    探討了復合地基中抗鋼筋的受壓受拉理及在拉壓循環荷載作用下的性狀,研究發現,隨拉壓循環次數的增加,應力向鋼筋集中,鋼筋承受的壓力隨著增大;無論上力大小,卸載后都有殘余變形,並隨著拉循環次數的增加而緩緩增加;抗碎石破壞性狀明顯,可明確的得到抗碎石的破壞荷載。
  7. Meanwhile, it does not need a extra time to be carried out. it can continuously work during the excavation of trenches, so whole work cycle can be reduced. anchors and layers of shot concrete have replaced the traditional steel frames and piles, including concrete piles, steel piles, and they can largely economize construction materials, such as steel and concrete, reduce the amount of soil that would be excavated out, and improve work conditions

    錨桿施工械及設備作業空間小,可為各種地形及場地使用,同時,它不獨占工期,而隨基坑開挖同步、流水進行,節約工期;用錨桿及噴射硅面層代替傳統的鋼支撐和(硅、鋼板) ,能夠大量節省鋼材、硅等建材,減少土方開挖量且能改善施工條件;其次錨桿的預加應力可以通過抗實驗來獲得。
分享友人