進出隧洞 的英文怎麼說

中文拼音 [jìnchūsuìdòng]
進出隧洞 英文
access tunnel
  • : 進構詞成分。
  • : Ⅰ名詞1. (隧道; 地道) tunnel; underground pass2. [書面語] (道路) road3. (郊外的地方) suburbsⅡ動詞[書面語] (旋轉) turn
  • : Ⅰ名詞(物體上穿通的或凹入較深的部分; 窟窿; 洞穴) hole; cavity Ⅱ形容詞(深遠; 透徹) profound; thorough; clear
  • 進出 : 1. (進來和出去) pass in and out; get in and out 2. (收入和支出) receipts and payments; turnover
  1. The impacts of both the velocity head and momentum distribution in the t - junction of a tailrace surge tank on the critical stable sectional area of the tank were analyzed by using gardel ' s empirical equations for t - junction flow. based on thoma ' s theory, a formula of the critical stable sectional area is derived. 5

    基於gardel關於三通管水頭損失的經驗公式,研究分析了連接管處的速度水頭以及調壓室水體與尾水水體之間的動量交換,對有連接管的尾水調壓室穩定斷面積的影響,並在托馬( thoma )假定基礎上,推導相應的調壓室穩定斷面的計算公式; 5
  2. However, along with the increasing of construction quantity of the infrastructure of irrigation works, traffic, communication etc., newer and higher requirement of geotechnical anchoring are made in slope, major dam, bridge, tunnel, deep foundation ditch engineering and the construction engineering such as anti - capsize, anti - float, anti - slippage engineering of the buildings. for example, self - intension of rock and soil is required to exploit better ; carrying capacity of anchor increase according to anchoring length ; anchor should be sufficiently lasting and should not influence the exploitation of adjoining stratum

    但另一方面,隨著我國水利、交通、通訊等基礎設施建設力度的加大,邊坡、大壩、橋梁、、深基坑以及建築結構物的抗傾倒、抗浮力、抗滑移等建設工程將對巖土錨固提一些新的和更高的要求:如要求一步調用巖土體的自身強度,錨桿應具有足夠的耐久性,錨桿的使用應不影響周邊地層的開發等。
  3. In this paper, we study the most serious damming section of the east - one main canal, which is from the entrance of the hao wan flume ( chainage12 + 123. 6 ) to the exit of shang tian yuan tunnel ( chainage24 + 091. 1 ). the main content is analyzing the flow characteristic of the canal, setting up mathematical model of the discharge condition of the east - one main canal, according to the survey section and actual roughness factors, building, bend and so on, we divided the canal into more than loocaculation segments. each segment is calculated by microsoft excel electrical table through computer as permanent transition flow of non - prismatic channel

    本論文研究的渠段為陸渾灌區東一乾渠壅水最為嚴重的渠段,從郝灣渡槽口(樁號12 + 123 . 6 )至上天院口(樁號24 + 091 . 1 ) ,其主要內容是,分析渠道水流特徵,建立東一乾渠輸水狀況的數學模型,根據測量斷面及實際糙率、建築物、彎道等因素的不同,將渠道劃分成120多個計算段,每段按非稜柱體恆定漸變流,運用microsoftexcel電子表格行編程計算。
  4. Depending on how the ground surface is denuded, the feature of the current crustal stress field and rock stress environment can be calculated analyzing the result in this paper : by analyzing the recovering feature of the elastic deformation of the rockmass in unload - stage under various pressures, it has been found there is close relationship between the recovering degree of the elastic deformation of the rockmass and the unloading degree of the pressure the direction of the major principal stress in the crustal stress field is not consistent with the direction of the crushing stress regional tectonics borne during the last tectonic movement. the evolving degree of the regional geomorphology evidently affects the current crustal stress field, which changes from the self - weight stress field to the horizontal stress field, with the changing of the eroding degree of the regional geomorphology ranging from valley area to hilly country to flat country. in valley area, where there is two stress belts, the bankslope s tress belt and the self - weight stress belt within the mountain. the direction of the major principal stress is nearly parallel to the ground surface and inclines towards the valley in the bankslope stress belt. it is nearly vertical in the self - weight stress belt

    通過本文的研究成果,根據區域性地貌的演化特徵,我們可以大致地對現今地應力場行判斷:在分級卸荷條件下,巖體中彈性變形的恢復具有明顯的規律性,這種規律對于研究地應力場的演變是有幫助的;地應力場中最大主應力方向與區域構造形跡在最近的構造運動中所受區域性擠壓應力的方向無明顯的對應性;區域性地貌形態的演化程度對現今地應力場的特徵具明顯的影響,隨著區域性地貌侵蝕程度由峽谷區、丘陵區、平原區的變化,現今地應力場特徵由自重應力場、水平應力場為主含少量自重應力場特徵向水平應力場的規律變化;在峽谷區,山體中具有兩個應力帶:自重應力帶和卸荷應力帶,最大主應力方向在卸荷應力帶中近平行於坡面並傾向于河谷、在自重應力帶中近於直立;根據原始地面遭剝蝕的程度,可以大致地估算最大主應力和中間主應力的量值和方向;在丘陵區和平原區,最大主應力的方向近於水平,並與附近區域性侵蝕盆地和河流的展布方向基本平行,根據原始地面遭剝蝕的程度,可以大致估算其最大主應力的量值;根據區域性地貌形態的特徵來分析工程區的現今地應力場特徵,並而大致了解巖石的應力環境,這種分析方法得的結論與許多實際的地應力測試成果基本一致,對于大型水電工程地下廠房和壓力的設計是有所幫助的。
  5. This paper presents a new synthesized statistical method for acoustic detection data processing based on the contrast to and statistic & analysis on a great deal of data of acoustic detection, elastic modulus and tunnel operation conditions, which has been applied in many hydropower projects

    為此,通過對大量聲波、彈模數據和工程運行情況行對比、統計和分析,總結了一種針對高壓固結灌漿效果的多種聲波檢測綜合數據統計方法,並已用於多個水電項目中。
  6. Finally, as a example, the author demostrates the design process of a hydraulic tunnel by using the cad software autosd. the program displayed approving outcome, automatically exporting drawings and reports

    最後,作者應用一個設計的實例對autosd系統行了驗證,系統自動繪制設計圖紙和簡要報告,取得了滿意的結果。
  7. As to the tunnels of jinping hydroelectric power station in sicuan province, the thesis discusses how to reasonably consider the initial stress field when designing a large - scale tunnel with high initial stress and deep buried. first, by analyzing of the rock lab tests and discusses the feature of regional geomorphology. explains the production of initial stress field, analyze the initial stress of jinping hydroelectric power station ; second, using the fem, the paper creates the real model of region. according to the results of stress measurement point, by combining of ann and fem to decide the boundary condition, the paper calculates the initial stress field ; at last, the paper analyzes the influence of the initial stress field formed from different condition on the deformation and stress of the surrounding rock, and the main factor to influence the initial stress. on the basis of the former work, the author proposes some proposals, which will be helpful for studying and designing of the similar undergroun d engineering

    首先從巖體的應力?變形的特性入手,並結合工程區域的地形地貌特徵,對巖體初始地應力場的形成做解釋,結合錦屏水電站初始地應力的現狀提了將地應力場行分帶;然後建立整個工程區的實體模型,在地質分析的基礎上,以工程區右半部分為代表,參照實測點的初始地應力值,採用了神經網路與有限元相結合的方法反演了該區域的初始地應力場;最後模擬的開挖,通過計算比較分析了初始地應力場對處于不同應力帶內的圍巖穩定性的影響,在此基礎上提了作者的建議,力圖為該類工程的研究設計工作提供有益的幫助。
  8. ( 2 ) the method of finite element discrete and optimal parameter back analysis is adopted. ( 3 ) concentrated on the question of high external water pressure of the deep - lying tunnel, the basic theory and method calculating external water pressure are systematically studied. ( 4 ) based on jinping cascade 2 hydropower station, numerical simulation rain infiltration of seepage field under different drainage pattern and grouting pattern are studied, also, the high external water pressure is analyzed and studied and some seepage control measures are put forward

    ( 2 )採用有限元離散?優化法行參數的反演分析; ( 3 )針對深埋的高外水壓力問題,一步分析和研究了襯砌水荷載及外水壓力的作用機理和計算方法; ( 4 )以錦屏二級水電站深埋長引水作為本文的主要研究對象,採用考慮降雨入滲滲流場分析的方法對排水方案和灌漿封堵方案不同情況下的滲流場的水頭分佈行了數值模擬,並對其外水壓力行了分析和研究,提了滲流控制的具體措施。
  9. All water conveyance and water discharge structures are designed to locate at right bank strip ridge, due to special topography and land form. large excavation area and steep slope raising from close plan locations of adjacent structure lead to slope stability. in general, slope stability analysis and treatment are concerns of zipingpu project

    由於其特殊的地形、地貌,工程的各輸、泄水建築物共7條均布置在右岸條形山脊內,各相鄰建築物口的平面位置距離較近,開挖范圍大、坡度高且陡,存在著大量因開挖而形成的高邊坡穩定問題。
  10. Finally, based on the stresses analysis of the rock mass, the existed design rules are discussed, and a new method to predict the safe location of the pressure tunnels is developed

    最後,根據對圍巖應力場的分析,對現有確定壓力最小覆蓋層的經驗準則行了評價,提一種新的確定壓力位置的方法。
  11. This subject directly investigates 14 construction enterprises and more than 40 construction sites. the types of the projects involve railway, bridges, tunnel, municipal, road, industry and civil construction, airport runway, hydraulic tunnel and others. this paper deeply analyzes and assesses the occupational health and safety management actuality of the construction site, points out the main problems in the process of hazard identification, risk assessment and risk control, and also analyzes why these problems exist

    該課題研究直接調查了十四家施工企業和四十多個項目施工現場,項目類型涉及鐵路工程、市政公用工程、公路工程、房屋建築工程、機場場道工程、橋梁工程、水工工程、土石方工程等,對施工現場實際的職業健康安全管理現狀行深入的分析、評估,指了危險源辨識、風險評價、風險控制過程存在的主要問題,並分析了為什麼會存在這樣的問題。
  12. The flow in outlet structure of pressure tunnel is simulated by using monte carlo method with irregular random walking grids in this paper

    摘要利用不規則游動網格的蒙特卡羅法對有壓口段水流行了數值模擬。
  13. Autosd software is composed of 4 modules : management of tunnel design processes, management of tunnel design data, computation and resultes output of tunnel design, and 20 sub - modules

    系統分設設計程管理、設計數據管理、設計計算模塊、設計輸模塊四大功能塊及其下二十個子功能模塊。
  14. The construction of the multiple - arch tunnel is deeply related to the form of center partition, the tunnel ' s section and excavation method etc. the change regularities of stress field caused by excavation are studied by 4 multiple - arch unlined tunnel model tests. the difference in lining for various multiple - arch sections is analyzed and the mechanics characteristics of center partition is discussed. then, a reasonable construction method for multiple - arch tunnel and a better section are put forward

    通過4個連拱模型試驗,研究了連拱毛開挖引起的應力場變化規律,對不同的連拱斷面的襯砌受力差異行了深入的分析,同時對中隔墻的受力特點也作了探討,提了合理的連拱道構築方法及優化斷面圖。
  15. The paper introduces the progress and the statue quo of tunnel portal construction, discusses the condition to employ full face method, bench cut method, single side heading method and double sides heading method of portal construction, points out advantages and disadvantages of these methods. the order to adopt these methods of single track, double track and tri - track tunnel in shallow - depth, uneven pressure and incompact ground is also advised after compare

    討論了全斷面法、臺階法、單側壁導坑法和雙側壁導坑法在口段施工中的使用條件和優缺點,對這四種施工方法從各個方面行了比選,提了單線、雙線和三線道的口段處于淺埋、偏壓、鬆散的地層中時各種施工方法選擇的先後順序。
  16. For this reason, this paper puts forward a guide wall should be increased to reduce the sand flowing into the tunnel and increase sand - flushing effectiveness of sand gate

    為此,提了增設一道導墻的方案,以減少引水沙並提高沖沙閘排沙效果。
  17. Then we simulate the common excavating methods of double - arc tunnel respectively, analyze the stress and strain of wall rock and support structure of each method, and recommend the best excavating method to construct double - arc tunnel in wall rocks of ii. then we analyze the " three headings method " in detail, and also simulate the effect of construction factor, stress releasing coefficient and secondary lining

    對實際工程中最常用的三種開挖方法分別行了施工模擬,分析了它們各自的圍巖和支護的受力變形規律,經比較后,得了三導法是類圍巖中修建連拱道的較好開挖方法的結論。
  18. ( 4 ) the dynamic data forecasting model of ground settlement is studied, a new prediction model of grey - time serial with time - varying parameters characters is proposed

    ( 4 )研究了施工中地表沉降動態預測模型,提了時變參數灰色?時序動態預測模型,並建立了一種改的時變灰色模型。
  19. This paper, focusing on the construction in the tunnel section with the worse geological conditions, discusses systematically the theory and the actual application on natm, and puts forward the proposal that the natural states of surrounding rock must be disturbed as small as possible and the self - loading of rock should be made full use of. as emphasizing the main point of the method the study of doing extensively the work of the measurements and the relevent analysis in the site takes up the much space in the paper

    本文針對不良地質地段的施工,系統論述了新奧法的理論和在工程實踐中的應用,提了應盡可能少地擾動圍巖的自然狀況並充分利用圍巖自身承載力;重點是要在現場廣泛開展監測工作和相應的資料分析;然後根據現場的監測信息以及對圍巖的觀察和認識,對設計行及時反饋,及時優化支護和施工參數用於和指導現場施工。
  20. There are large words in slope design and slope deformation analysis with monitoring involved, on basis of geology of slopes at nos. 1 and 2 diversion tunnel inlets and actual project conditions of zipingpu project. interior and exterior factors and conditions causing deformation are obtained from analysis. special measures to control deformation are taken to ensure long - term stability, such as consolidation

    本文以分析紫坪鋪水利樞紐1 ~ # 、 2 ~ #導流口邊坡為主,根據導流口的地質及具體的工程環境及條件,對工程中的高邊坡設計所遇到的一些問題行了分析和闡述;並採用了一定的監測手段,對施工過程中邊坡產生的變形,行了觀測分析,通過綜合分析,找邊坡變形的內在因素和外部條件,有針對性的採取工程處理措施。
分享友人