And study the quantified methodology of self - restraint the source, the soil erosion reducing, the soil nutrient prediction and reservoir mud alluvial prediction, and applies the model count the water conservation benefit in lingchuan county magedang experimental unit in shanxi province
並分別探討了涵養水源、減少土壤侵蝕、減少土壤養分流失及減少水庫泥沙淤積的效益量化計算方法,以山西省陵川縣馬屹當小水電代燃料試點工程為例進行了水土保持效益的實例計算。The paper also advances some opinion and measures based on runoff characteristic to improve the reservoir operation, and then analyses the corresponding results
針對流域徑流特點,按照增加水庫調節水量,提高供水效益,減緩水庫淤積發展的要求,提出了水庫運用方式的改進意見和措施,並對其效果進行了分析。For studying the regulation rules of the sediment of the second phase project, and studying the reservoir capacity loss caused by deposition, the amount of sediment passing through the turbines, and the deposition and flow regime near the intake of the pump - turbines, the deposition of the reservoir was studied
為了研究蒲石河抽水蓄能電站二期工程泥沙調度方案,對多個方案的水庫淤積損失、過機沙量、取水口附近的泥沙淤積和水流流態,進行了水庫沖淤研究。Firstly, we account for the former made and the sand selected are reasonable by experiments. then we develop the first project carrying the experiment for filling up of 30 years. contrasted with the count, the results have no difference, we carried two experiments under different water levers by the actually facts if engineering work in early days. by the result, we know that the gross of fill up have no difference
本文從白石水庫泥沙模型試驗入手,模型試驗首先通過模型糙率和模型選沙驗證試驗,說明模型製作和選沙是合理的;然後開展初設方案30年運用水庫淤積試驗,並與數模計算對比,基本相同;試驗結合工程初期運用實際情況,進行了兩個不同初期運用水位方案的對比試驗,從兩個方案試驗結果看,初期運用的兩個方案淤積總量差別不大,而從效益看,方案二優于方案一。According to the fact of the engineering, the optimal modeling when fenhe first reservoir operated alone are first made. after getting the regularity, in order to consider fenhe second reservoir that had been finished essentially and shanxi wanjiazhai yellow river diversion project, not only the object of minimum water shortage for satisfying the water use demanded mainly by user are founded, but also the object of minimum the reservoir deposition was found. in order to prevent the water use demanded by city and industry from excessively concentrated water shortage, the object of minimum water shortage required to be the equable shortage
本文在對來水分析基礎上,對太原市需水庫供水的用水進行了預測,結合工程實際,先對汾河一庫單獨運行時進行優化模擬,得出規律后,考慮已基本完工的汾河二庫及引黃南干工程,建立了以滿足用戶用水為主要目標的「缺水量最小」目標和減少水庫淤積的「水庫淤積量」最小的目標,其中「缺水量」最小目標要求是均勻的短缺,避免過分集中而影響了城市及工農業用水。The paper starts with the reservoir sedimentation, operation mode and catchment runoff characteristics. the study comprises of distributing of runoff and sediment in the catchment, the influence and trend of sedimentation and water storage under different operation mode
課題研究主要從水庫淤積狀況、運用方式和流域徑流特徵分析入手,闡述了流域徑流、泥沙時段分佈,研究了不同運用方式下水庫沖淤的主要影響因素及變化趨勢,分析了不同運用方式時水庫淤積情況和攔蓄水量。Many geological and hydrological factors of the river section, where the yellow river water intake engineering is laid out, such as the capacity of the reservoirs along the river section upstream and downstream, the rate of the flow discharge, the erosion and silt of the watercourse, the form of the riverbed and the water current, ice tuck, the convergence of the upstream branches of the river section, flood crest, sand crest size, the capacity for flood discharge of the watercourse, the effect of flood control structure around and the impacts on surrounding environment and the third person " s legitimate rights and interests, should be considered
黃河取水工程的布設要考慮工程所處河段的地質水文等諸多因素。如該河段上下游水庫的庫容,泄水流量、河道沖刷、淤積、河床形態、水流形態、冰塞、河段上游的支流匯入、洪峰、沙峰的大小、河道行洪能力的大小、周圍防洪工程的影響及對周圍環境和第三人合法權益的影響等等。For the reasons of accumulated soils and sands and the amount of precipitation, the volume in the reservoir is dynamic. if the volume in the reservoir is not dispatched correctly, it will result in the overflowing of the dam bank of the reservoir, even in the collapsing of the darn
庫容又是水庫調度不可忽視的問題,而庫容又與水庫的橫、縱斷面、水位、水深有關,由於泥沙淤積、降水量多少等原因,水庫水量是動態的,不對水庫水量正確調度,會在大洪水時,造成水庫堤壩漫溢甚至垮壩。Based on the analysis of satellite images of various periods, landform data and river channel transverse section evolution in the lower yellow river, the characteristics of the river channel boundary condition changes at different location are clarified as middle flood channel flood transport width and area are evidently decreased especially for the main channel with comparison to 1950s, beach area that is unimpeded before become blocked because of road, irrigation channel constructed on it, and consequently intensify high edge of beach and lowering dyke and river
在現場查勘的基礎上,通過對丹江口水庫和小浪底水庫攔沙初期下遊河道演變、排洪能力變化特點的對比,分析了黃河下游防洪面臨的新形勢:小浪底水庫攔沙初期,下遊河道發生沖刷,但艾山以下窄河段沖淤變化不大,近年來形成的淤積萎縮的狀況難以很快改觀,游蕩性河段調整劇烈,工程出險機遇增大,河道水位流量關系中水流量以下部分同流量水位明顯降低,中水流量以上部分水位降低幅度可能會明顯偏小,防洪形勢仍不容樂觀。Hydroelectric power exploitation can reduce sediment disposal, lengthen life of power plants in lower stream, control stream, better water quality, and reduce contamination etc. considering the structure of power of sichuan province and pointing out its six problems in power development, this thesis comes up with sustainale development strategy of sichuan hydroelectric power exploitation, that is, prefentially exploit large scale hydropower plant which has good water - adapting capability, comprehensively use water resource, try to reduce cost caused by drowning, stimulate rotating exploitation, well deal with settlement of people in hydroproject construction, and alleviate contamination
論述水電開發在減緩泥沙淤積、延長下游水電站壽命、調控水流、提高供水量、改善水質、提供清潔能源、減少環境污染等方面對長江上游生態屏障建設的作用。本文研究分析了四川水電開發的可持續發展戰略,首先對四川省電力結構現狀進行了分析,指出目前四川電力發展存在的六個主要問題,從優先開發具有良好調節性能的大型水電站、綜合利用好水資源,盡最大可能減少水庫淹沒損失,積極推進流域梯級滾動綜合開發,處理好水庫移民關系,減輕對環境的不利影響等六個方面論述了水電開發的可持續發展戰略。B ) utilizing dong zhuang reservoir to adjust during on year. thus can decrease the sediment deposit of lower wei - river as result small flood and non - flood season
利用東莊水庫調節涇河小流量洪水,進行年內調節,盡可能減少小洪水和非汛期小水對渭河下游的淤積。Qualitative analysis on the effect of flood control and engineering safety -, seizing lots of water conservancy effective adjust storage. then making water level risen and reservoir backwater enlarged in the same flow level ? effect on beach and the buildings across river, soil salinization caused by flow from a lower to a higher place and unsmooth groundwater drainage destroy of travel resource caused by disorder enclose tideland for cultivation in reservoir silt up flood plain are given, then presents enclose tideland for cultivation dyke is important cause which water level rise in reservoir
本文從青銅峽水庫泥沙淤積入手,分析水庫泥沙淤積特性和庫區圍墾堤開發利用淤積灘地的現狀,對防洪安全及工程安全的影響、侵佔大量的有效調蓄庫容、造成同級流量下水庫水位抬升水庫回水上延、對沿岸及過河建築構成影響、因水位抬升致使庫區周邊灌區地下水排水不暢乃至倒灌而造成土地鹽堿化、對水庫庫區大量淤積灘地無序圍墾造成旅遊資源破壞等五方面影響的定性分析,提出庫區圍墾堤是水庫水位抬升的重要原因。On the one hand, the sediment density current often does a great harm to the reservoir, and causes a big loss of reservoir ' s storage capacity or makes reservoir severe deposition ; on the other hand, sediment outflow by density current is an effective measure to mitigate sedimentation
異重流(本論文中主要指因含沙量的差異而形成的渾水異重流)一方面常常給水庫帶來嚴重的危害,加速水庫的淤積和庫容的損失;但另一方面它又為水庫排沙提供了一種極為有效的途徑? ?水庫異重流排沙。The comparison between the experimental data with numerical simulation show that the model have a higher precision in the lateral scouring and sedimentation deformation, time interval quantity of deposition, and output sediment concentration process during sand peak at various cross section and is applied fairly good to practical engineering
青銅峽水庫的實測資料對模型驗證結果表明:模型在水庫不同斷面橫向沖淤變形、時段淤積量、沙峰期出庫含沙量過程都具有較高的精度,能較好地運用於工程實際。Traditional irrigation, however, has degraded the soil in many areas, and the reservoirs behind dams can quickly fill up with silt, reducing their storage capacity and depriving downstream farmers of fertile sediments
然而傳統的灌溉法已對多處地區的土壤造成侵蝕現象,而水壩攔截水而形成的水庫,也很快就有沙石淤積,除了降低水庫的蓄水量,還使得下游農民喪失了肥沃的沉積土。The sediment problems of this project in design is that the deposition of sediment causing the permanent loss of reservoir capacity. the measure of enlarging the discharging of water and sediment can reduce deposition, but the concentration of sediment is bigger and much sediment passes through the pump - turbines
減少水庫庫容淤積損失,加大排沙量,會造成在發生洪水時期水庫內含沙量加大,抽水時會有更多的泥沙過機,機組因泥沙而磨損。分享友人