深開挖 的英文怎麼說

中文拼音 [shēnkāi]
深開挖 英文
deeexcavation
  • : Ⅰ形容詞1 (從上到下或從外到里的距離大) deep 2 (深奧) difficult; profound 3 (深刻; 深入) thor...
  • : 動詞(用工具或手從物體的表面向里掘取) dig; excavate; scoop
  1. This thesis tries to solve the problems in the design and construction of jinping cascade 2 hydropower station. a typical section is selected to analysis seepage, seepage control and fem numerical simulation. the influence of different plans of excavation and support on seepage field of subsurface water and stability of adjoining rock are studied. the homologous support pattern is suggested according to the research results

    本文就錦屏二級水電站(一期)埋長隧洞的設計和施工中面臨的一些問題,選取隧洞的一個典型斷面進行滲流、滲控分析和及支護的有限元數值模擬,從而就埋隧洞不同的及支護方式對地下水滲流場及圍巖穩定性的影響和所應採取的支護措施等方面進行了探索、研究。
  2. In the paper, the theory of geomechanics and the engineering are collaborate coherently. some results can be applied to excavation constructions in some degree

    本文將軟土實踐與巖土力學理論緊密結合,部分研究成果對工程實際具有一定應用價值。
  3. This procedure can imitate the single well pumps water the chronometer calculates at all point water level in district declines deep with horary variety ; study the sport law of the rivers ; solve definitely flow draw water issue wanton boundary the wells of termses, predict that dives under water in the location, guide and construct and excavate the progress, appraise the rationality of the precipitation scheme

    此程序可以模擬單井抽水時計算區域各點水位降隨時間的變化,研究水流運動規律;求解任意邊界條件下的井定流量抽水問題,預測潛水位,指導施工進度,評價降水方案的合理性。
  4. In the process of construction, some special geological hazards will be met because of the great depth and long distance, such as high external waterpressure, watergushing, high geostress, rockburst, high geotemperature and nocuous gas and so on. these geological hazards become the main restricted factors of tunnel construction

    大埋將使隧洞施工時遭遇到如高外水壓及高壓涌水、高地應力及巖爆、高地溫、高瓦斯有害氣體等一系列地質災害問題,這成為制約埋隧洞建設快速發展的主要因素。
  5. The key technique of this project is the design and construction of four deep - lying long runnels. their length, diameter and maximum bury - depth are 18 km, llm, 2500 m

    這一工程的關鍵技術是四條長達18公里、洞徑11米、最大埋2500米左右埋長隧洞的設計和施工。
  6. A novel method based on artificial neural network bp algorithm to perform the parametric identification in deep foundation excavation is proposed hi the paper. taking in situs measurements as network input and parameters to be identified as network output, the network is trained with the samples obtained from fem computation

    將某些現場實測值作為網路的輸入,土層物性參數作為網路的輸出,通過有限元正分析模型取得學習樣本來訓練網路,從而達到對基坑過程中的多層土體的物性參數進行辨識的目的。
  7. Based on the research works of predecessor, the theory on the displacement of soil strata in deep foundation excavation construction and its application are studied in detail. by analysing the supervision, statistics from, the practical excavation engineering, soil rheology is thought to be the main reason of the displacement heavy of the soft soil and the destruction of the enclosure structure, in deep foundation excavation construction on condition of the high theriomorphic of enclosure structure and good seepage resitting

    本文在已有研究成果的基礎上,對大面積軟土基坑時土層變位理論及應用進行了探討:依據現場監測數據,推導出時軟土變形的經驗公式,分析了軟土在圍護結構剛度大、基坑防滲效果好的條件下,基坑土層變位、圍護結構受力破壞發展的主要原因。
  8. When excavating deep foundation ditch in the lake sediment that filled with deep and thick silt, it is a common technical problem that the upheave which caused by relief loads leading to slope destabilization

    摘要在湖泊相沉積的厚淤泥土場地基坑,由於坑底卸荷隆起導致基坑邊坡位移、失穩是常見的技術難題。
  9. " prestress anchor ribbed beam support system " is a new practical support technology which came from soil nailing walls system and un - embedded rank of piles with anchors support system that has been used successfully for 4 years by the author and his company named qingdao deep foundation stabilization engineering co., ltd. it " s mechanism is similar to rank of piles with anchors support system that can not be inserted into the bottom of foundation trench, but it " s ribbed beams are used to replace rank of piles made before excavation so the work cycle can be shortened and the support system cost can be reduced ; meanwhile this system maintains the soil nailing wall " s convenience of digging and supporting

    「預應力錨桿肋梁支護技術」是筆者及所在單位歷時四年在土釘墻和無嵌入多錨排樁兩種支護體系基礎上發應用成功的一種新型實用性支護技術。其支護機理類似於未嵌入坑底的排樁多錨支護,只是由肋梁代替了前施工的排樁從而提前工期並降低支護造價;同時繼承了土釘墻隨隨支護的機動靈活性。自1998年至今該技術已在青島、濟南、煙臺等十幾個基坑和高邊坡工程中成功應用。
  10. In other words, soil creep may make significant contributions to diaphragm wall displacement and ground settlement in a deep excavation project in soft clay strata

    也就是說,對一個座落於粘土地層的深開挖工程而言,土壤潛變可能對壁體側向變形及地表沈陷有顯著的貢獻。
  11. This paper also presents a quantitative method to evaluate this creep effect

    本研究也提出一個可以評估深開挖土壤潛變效應的量化評估方法。
  12. Slope instability problems ; piles ; excavations ; tunnels

    斜坡的不穩定性;樁;深開挖;隧道
  13. Deep excavation and building protection

    深開挖工程及建物保護
  14. Practice amp; discussion on non curtain deep excavating dewatering engineering

    無帷幕深開挖降水工程實踐及問題探討
  15. Bridges, high - rise buildings, underground structures, tunnels, retaining structures for deep excavations

    橋梁高層建築地下結構物隧道深開挖擋土結構
  16. Not only deformation was controlled, but also cost and engineering time were reduced

    作為大面積、深開挖的基坑工程既控制基坑變形又達到降低工程造價、縮短工期的目的。
  17. This paper presents the time - dependent performance of an well - instrumented excavation case using the top - down construction method

    摘要本文以一個有完整監測資料之深開挖案例來探討其依時變形行為。
  18. In this paper, author compare with shenzhen holiday plaza project ( be known as firstly deepest foundation pit, deepest excavation depth is 21m ), use combinative method for theory guidance, test study, simulation analysis, project application and information feedback, entirely and deeply study prestress anchor cable composite soil nail, and also make a pilot study for deformation of pile anchor composite soil nail

    本文以圳假日廣場基坑支護工程(號稱「圳第一坑」 ,最深開挖21m )為背景,採用了理論指導、試驗研究、模擬分析、工程應用和信息反饋相結合的方法,對預應力錨索復合土釘支護結構進行了全面入的研究,對樁錨式復合土釘支護結構的變形進行了初步研究。
  19. This manner of change reflected the great influence of texture to rock mass quality. rock mass mechanical parameters corresponding to individual rock mass quality at different levels are determined by means of correlation analysis and statistical analysis. results show that calculation outcomes match well with measured mechanical parameters

    研究結果表明:對于混凝土重力壩,按照現在的深開挖方案,壩肩后,土石方量高達820x10 『 m 『 ,且在72dri高程至坡頂將產生大范圍的破壞區,採用工程治理將帶來巨額的費用。
  20. The works included 24 bored piles of 2. 5 meters in diameter and 55 meters in depth, 500 meters long underground concrete diaphragm wall of 0. 8 meters thick and 25 meters deep, 450 pre - cast concrete pile of 0. 5 meters in diameter, 12 meters deep soil excavation with multi - layer post - tensioning shoring system, reinforced concrete pile caps and basement slabs

    其工程內容包括了24支直徑2 . 5米,達55米直入巖層的鉆孔樁,周長500米,度25米,厚度0 . 8米的地下連續混凝土墻, 450支直徑0 . 5米預制混凝土樁, 12米深開挖,多層水平鋼支撐系統,混凝土樁承臺及地庫底板結構。
分享友人