穿過體壁的 的英文怎麼說

中文拼音 [chuānguòde]
穿過體壁的 英文
transparietal
  • 穿 : Ⅰ動詞1 (破; 透) pierce through; penetrate 2 (通過孔、隙、空地等) pass through; cross; go thro...
  • : 過Ⅰ動詞[口語] (超越) go beyond the limit; undue; excessiveⅡ名詞(姓氏) a surname
  • : 體構詞成分。
  • : 名詞1 (墻) wall (of a house etc ) : 銅墻鐵壁 bastion of iron2 (作用像圍墻的部分) wall of st...
  • : 4次方是 The fourth power of 2 is direction
  • 穿過 : (通過; 越過) pass through; cross over; passage; passing; thread; through
  1. By comparing the dry plate pressures drop and distributions of velocities simulated on single valve with those of double valves, it was found that there was intense turbulence in the flow fields around fixed - valve, there were eddy areas between valve side orifices and tray wall, there were eddies above the valves too, these led to the complex behaviors of gas perforating valve, these had a great effect on the gas - liquid mass transfer process. at the same time, in order to prevent the disadvantageous effect of gas between one valve with another on the gas - liquid mass transfer, it was very effective to change the fields of gas perforating valve by folding the edges of valve

    對數值模擬得出單閥和雙閥塔板干板壓降及流場速度分佈分析對比后發現,固定閥周圍流場存在較強湍動,閥側孔與塔板面區域以及閥上方空間存在明顯渦流區,使氣穿閥后行為變得復雜,並對氣液傳質程產生重大影響;模擬結果表明,為防止和削弱固定閥間對沖造成「死區」對傳質帶來不利影響,通折邊來改變氣氣路是非常有效,模擬值與實驗值基本得到吻合。
  2. Secondly, this paper made some theoretic researches on its engineering classfication and applicable scope for this technology ; then combining with project example, this paper carried out scheme design for this technology, and compared some different kinds of underpinning scheme and node and structure design, and put forward the method of " reinforcce steel bar through column " to build pile cap beam, " resistant bend and shear anchored reinforce steel bar " to strengthen column consolidation effect, and the method of " steel plate hoop " to build reinforcing bar connection of the foundation beam, etc. in the process of the consturction scheme research and implement, this paper synthetically elaborated the organizaton for project construction, put forward the construction technical measure of specific aim on the artificial pile, and pile cap beam, and underground adding layer and structure stabilization, and overall structure stabilization and so on. for this project, adopt reinforcing bar concrete to brace hole wall to ensure the safety of engineering in the artificial pile construction, use flexible connection catch to make the cage hoisting easier to simplify the construction process, use the method of earthwork statified symmetrical balance in the process of underground adding layer excavation

    本文首先對于基礎托換與結構加固技術和意義、國內外發展狀況進行了綜合闡述;其次對該項技術工程分類及適應范圍進行了理論上分析研究;然後結合工程實例對該項技術進行了方案設計,對比幾種不同托換方案和節點及構造設計,提出了「通筋穿柱法」做承臺梁, 「抗彎抗剪錨筋法」強化柱加固效果, 「鋼板箍法」做地基梁鋼筋連接點等多項技術;在施工方案研究和實施程中,對于工程施工組織進行綜合闡述,並就人工挖孔樁、承臺梁、地下加層及結構加固、整結構穩定等專項施工方案提出有針對性施工技術措施,人工挖孔樁施工採用鋼筋砼護確保挖孔樁安全成型,使用柔性連接鉤進行鋼筋籠吊裝簡化施工工序;承臺梁施工採用梁主筋橫穿柱身化學膠錨固等;地下加層綜合施工技術採用土方分層對稱平衡開挖,分段挖土做筏基結構自穩等;最後對于該工程實施后效果分析,說明該項綜合施工技術可行性。
  3. The shearing layer is carried by the jet and the eddy is formed because of the instability and selective amplification of shearing layer which will propagate to the downstream. as the eddy impacts the impinging wall, a wave of pressure disturbance with certain frequency is induced. this wave then propagates to the upstream with high speed, and results in the overlap and amplification of the waves when the frequencies of them are close with each other

    當前噴嘴流束中不穩定擾動波在穿腔內剪切層時,剪切層對其有選擇放大作用,形成渦環結構,剪切流動中渦環與碰撞撞擊,在碰撞區域產生壓力擾動波並向上游反射,在上游剪切層分離處誘發新擾動產生,當新擾動與原擾動匹配時,射流上游就被不斷地受到周期性激勵,腔內就產生流自激振蕩並在後噴嘴出口形成脈沖射流。
  4. Based on the nodal mechanics theory and generalized displacement method, equations that the thin - wall cylinder pile is simulated with the beam element are derived. the influence of the number of beam element is researched, and conclusion that the number of beam element and the number of soil layer should be uniform is draw up

    應用節點力學基本理論和廣義位移法基本概念,推導了用梁單元模擬薄筒樁計算公式,研究了梁單元離散樁結構時梁單元數目對計算結果影響,得出了梁單元數量宜與樁穿土層數目相一致結論。
  5. Packaging pills with their own bodyguards ( in this case, molecules called protease inhibitors ) could enable protein - based drugs to survive, but it would not aid them in crossing the gut lining ; they are too big to slip into the blood as easily as more typical drugs, which generally consist of small molecules

    為藥物配備保鏢(上述例子保鏢分子稱為蛋白酶抑制劑) ,雖然可以讓蛋白質藥物保存下來,但卻無法幫助藥物穿,因為這些分子太大,無法像一般小分子藥物那般輕易進入血液,而且包覆層對藥物動力學(藥物進入血液速率以及停留在身組織與器官時間)控制能力也相當有限。
分享友人