濾水壩 的英文怎麼說
中文拼音 [lǜshuǐbà]
濾水壩
英文
filter dam-
A brief introduction is given to the treatment of the zeya dam foundation, principles of seepage control and design of the concrete face rockfill dam of the zeya reservoir. as for the excavation of the sand - gravel zones, except the toe slab and its 1 / 9 bottom width down stream, the alluvial layers are excavated to the micro - weathered rocks, while the other sections remain unexcavated. regarding to the treatment of the fracture zones, concrete filling is used for the toe slabs and semi - permeable materials are used for other section. according to the construction characteristics, a filter is placed in the down stream embankment foot. to improve the integrity of the dam foundation and anti - seepage capability consolidation grouting and curtain grouting are adopted. as a result safety, economic benefit, convenience in construction and good performace are achieved
簡要論述澤雅水庫面板堆石壩壩基處理和防滲的原則及設計要點.趾板基礎和堆石體各區砂礫石基礎開挖,除趾板與其下游1 / 9底寬范圍以及壩腳挖除沖積層至弱風化(局部微風化)基巖外,其餘部分均予以保留.斷層破碎帶處理,趾板部位採用混凝土塞,其它部位採用半透水料置換,並根據本工程特點在下游壩腳加設了反濾層.為提高壩基的整體性和防滲性能,對趾板進行了固結和帷幕灌漿.達到了安全、經濟、便於施工的目的,運行情況良好,可為面板堆石壩的設計和研究提供參考與借鑒In order to understand the characteristics and mechanism of flow washout for the crevice of core wall in earth - rock dam, according to the exemple of crack washout test for the core of heihe dam, constant water level washout test and changing water level washout test are adopted differently, the process of test and the character of the flow washout for the core crack are gone into particulars
摘要為了解水流沖刷作用下反濾層對土石壩心墻裂縫發展保護作用的特點和機理,以黑河土石壩心墻裂縫沖刷試驗為例,分別採用常水頭和變水頭兩種方法,探討了土石壩心墻裂縫在水流沖刷過程中的特點。In this paper, regarding the analysis of stability factors of majiatian tailings fill dam, namely regional geologic structure, rock - soil body of dam foundation, poor geology phenomenon, leach consolidation and chemical consolidation of tailings, seepage water of dam body and king - size flood water of majiatian tailings reservoir, a preliminary demonstration on probability of earthquake liquefaction and seepage failure of dam bodys tailings sand soil, of the dam body failure resulted from abutment landslide and of the flood water overflowing crest, as well as on the contribution of leach consolidation and chemical consolidation of tailings to the stability of dam body has been performed
通過對馬家田尾礦庫區域地質構造、庫區不良地質觀察、尾礦淋濾固結和化學固結、壩體滲透水和庫區特大洪水等因素對馬家田尾礦堆積壩體穩定性影響的分析,初步論證了壩體尾礦砂土的地震液化、滲透破壞、壩肩滑坡使壩體失穩和洪水漫頂的可能性,以及尾礦淋濾固結和化學固結作用有助於壩體的穩定性。In this paper, regarding the analysis of stability factors of majiatian tailings fill dam, namely regional geologic structure, rock - soil body of dam foundation, poor geology phenomenon, leach consolidation and chemical consolidation of tailings, seepage water of dam body and king - size flood water of majiatian tailings reservoir, a preliminary demonstration on probability of earthquake liquefaction and seepage failure of dam body ' s tailings sand soil, of the dam body failure resulted from abutment landslide and of the flood water overflowing crest, as well as on the contribution of leach consolidation and chemical consolidation of tailings to the stability of dam body has been performed
通過對馬家田尾礦庫區域地質構造、庫區不良地質觀察、尾礦淋濾固結和化學固結、壩體滲透水和庫區特大洪水等因素對馬家田尾礦堆積壩體穩定性影響的分析,初步論證了壩體尾礦砂土的地震液化、滲透破壞、壩肩滑坡使壩體失穩和洪水漫頂的可能性,以及尾礦淋濾固結和化學固結作用有助於壩體的穩定性。The whole project comprised the building of the dam, a 2, 428 - yard tunnel driven through the wong nai chung gap valley and a 5, 500 - yard brick and stone aqueduct to connect the reservoir with the storage tank and filter beds at albany road. each day the volume of water being conveyed reached 7 million gallons. the 6 filter beds of the project were situated on the eastern side of the albany nullah ; measuring 3, 245 sq
除水壩外,其他配套的工程包括: (一)一條長達2 , 428碼、貫穿黃泥涌峽谷的隧道; (二)一條長5 , 500碼的引水道,可連接水塘隧道的亞賓尼濾水池及配水庫,該引水道用石及磚砌成,每天可輸水700萬加侖; (三)位於亞賓尼水渠東部的六個過濾池,該濾水系統面積廣達3 , 245平方碼,深30尺,每天可過濾570萬加侖水,原水過濾后,經一條直徑18寸鐵水管,流入花園道與寶雲道交界的配水庫。Through field investigation and analysis indoor, with studying all hydrochemistry data in detail, including macro components and micro components, the author finds out the hydrochemistry feature of ground water. for further specifying the ground water system, with cluster analysis of macro components of surface water and ground water in total 147 samples and the analysis of micro components, including ree, the main ground water systems are distinguished by and large, especially the ground water system main of fault no. 7 and fault no. 15 water bearing belts which have differences at macro and micro components between the two ground water systems, moreover, the main hydrogeochemistry effects are established such as lixiviation, oxidization, precipitation and mixing effect, especially the mixing effect which result in the complexit y of the hydrochemistry of deep bearing tectonic fracture water. based on them, the hydro geological model of upper dam base is established, meanwhile the author summarizes the hydrochemistry feature of weathering crevice water, surface tectonic crevice water and deep tectonic crevice water
為此,本文以大崗山壩區水文地球化學問題為研究對象,通過野外調查和室內分析,詳細的研究了壩區水化學資料,包括宏量組分、微量組分,查明了壩區地下水水化學特徵,對採集的147個地表及地下水樣的宏量組分進行聚類分析,結合微量元素,稀土元素的研究,並應用二氧化硅地熱溫標確定了深部構造裂隙水的熱源深度,基本區分了壩區各個主要地下水水系,特別是以f7 、 f15斷裂含水帶為主的地下水系,它們的宏量組分、微量組分以及稀土等方面均存在差異,以此為基礎,結合壩區水文地質條件,建立了壩區的上壩址的水文地質模型,同時通過分析了壩區花崗巖區的水化學資料,確立了壩區主要的水文地球化學作用,分別為:溶濾作用、氧化作用、沉澱作用、以及混合作用,混合作用是導致深部承壓裂隙水水化學復雜的主要原因,並總結了壩區風化裂隙水、淺部構造裂隙水、深部構造裂隙水的水化學特徵。So far as the mixing material for building the earth - rock fill dam with clay core for shiquanhe hydropower station is concerned, the effect from the variation of the sand content for the filter material on the maximum dry density and the relevant parameters are to be determined within the variation area of the mixing mass ratio of ( 46 ~ 54 ) : ( 54 ~ 46 ) through this experiment, due to the max, dry density is largely influenced by the mixing ratio of both the lifter material and the clay and the sand content of the filter material, so as to determine the actual filling compactness of the mixing material of the core
摘要由於獅泉河水電站粘土心墻土石壩摻合料的最大幹密度受反濾料與粘土料的摻合比例、反濾料含砂率的影響較大,因此擬通過本試驗確定摻合質量比在( 46 ~ 54 ) : ( 54 ~ 46 )范圍變化時,反濾料含砂量變化對最大幹密度的影響程度及相關參數,從而確定心墻摻合料填築的實際壓實度。Shortly after the surveying work started the war broke out and the government was forced to halt the project. it was not until after the war in 1947, that the planning of the tai lam chung reservoir re - commenced
1947年,籌建大欖涌水塘計劃重新開展,草擬的藍圖包括了水壩、輸水隧道、輸水管、抽水站、濾水廠、配水庫等工程。The tai tam reservoir was situated higher than the tai tam intermediate reservoir. similarly, the latter was situated higher than the tai tam tuk reservoir. for these reasons, water stored in the tai tam tuk reservoir must be pumped upwards into the foothills of the tai tam valley in order to reach the tunnel portal of the tai tam reservoir, where water would gravitate to the supply system in central
無論是第一期或第二期的擴建工程,建造水壩都是工程的基礎,而建立抽水系統亦是重要一環,因大潭中水塘的水位比大潭上水塘低,大潭篤水塘更處于較大潭中水塘低的谷地,故大潭篤的存水必須依靠抽水機,才可運送至大潭水塘的輸水隧道,再經由大潭水塘輸送系統,調配至中區濾水系統經過濾后,才可供市民飲用。When completed the concrete dam was 150 ft. high and was the most magnificent of its kind in hong kong. aside from the main dam, there were three subsidiary dams, 37 kms of catchwaters, a water treatment works in tsuen wan and service reservoirs in lai chi kok, ma tau wei, diamond hill and ngau tau kok
除主壩外,還包括了三條副壩、長37公里的引水道、配合水塘供水的荃灣濾水廠,以及荔枝角、馬頭圍、鉆石山、牛頭角等配水庫,集水區廣達2 , 000畝。分享友人