挖土平臺 的英文怎麼說

中文拼音 [píngtái]
挖土平臺 英文
digging platform
  • : 動詞(用工具或手從物體的表面向里掘取) dig; excavate; scoop
  • : Ⅰ形容詞1 (沒有高低凹凸 不頃斜) flat; level; even; smooth 2 (高度相同; 不相上下) on the same l...
  • : 臺名詞(指臺州) short for taizhou (in zhejiang province)
  1. We need a mechanical digger to level the ground

    我們需要一掘機來地。
  2. As the balancing platform tends to make the barycenter move backward, a more balancing stress distribution under the wall, a higher and steadier wall can be achieved. furthermore, the resupine back of the downward wall not only works reasonably, but also can reduce the amount of excavation and filling obviously. so gravity retaining walls with balancing platform are applied heavily

    衡重式擋墻因具有衡重使墻身重心后移、墻底應力趨于衡,可提高擋高度、增強墻體穩定性;且仰斜式下墻不僅受力合理、還可減少開與回填量等優點而被大量採用。
  3. Secondly, this paper made some theoretic researches on its engineering classfication and applicable scope for this technology ; then combining with project example, this paper carried out scheme design for this technology, and compared some different kinds of underpinning scheme and node and structure design, and put forward the method of " reinforcce steel bar through column " to build pile cap beam, " resistant bend and shear anchored reinforce steel bar " to strengthen column consolidation effect, and the method of " steel plate hoop " to build reinforcing bar connection of the foundation beam, etc. in the process of the consturction scheme research and implement, this paper synthetically elaborated the organizaton for project construction, put forward the construction technical measure of specific aim on the artificial pile, and pile cap beam, and underground adding layer and structure stabilization, and overall structure stabilization and so on. for this project, adopt reinforcing bar concrete to brace hole wall to ensure the safety of engineering in the artificial pile construction, use flexible connection catch to make the cage hoisting easier to simplify the construction process, use the method of earthwork statified symmetrical balance in the process of underground adding layer excavation

    本文首先對于基礎托換與結構加固技術的目的和意義、國內外發展狀況進行了綜合闡述;其次對該項技術工程分類及適應范圍進行了理論上的分析研究;然後結合工程實例對該項技術進行了方案設計,對比幾種不同的托換方案和節點及構造設計,提出了「通筋穿柱法」做承梁, 「抗彎抗剪錨筋法」強化柱加固效果, 「鋼板箍法」做地基梁鋼筋連接點等多項技術;在施工方案的研究和實施過程中,對于工程施工組織進行綜合闡述,並就人工孔樁、承梁、地下加層及結構加固、整體結構穩定等專項施工方案提出有針對性的施工技術措施,人工孔樁施工採用鋼筋砼護壁確保孔樁的安全成型,使用柔性連接鉤進行鋼筋籠吊裝簡化施工工序;承梁施工採用梁主筋橫穿柱身化學膠錨固等;地下加層綜合施工技術採用方分層對稱衡開,分段做筏基結構自穩等;最後對于該工程實施后的效果分析,說明該項綜合施工技術的可行性。
  4. Applying the basic theories of spatial data mining and geomorphology, taking the loess plateau of north shaanxi province, china as the research area, this dissertation explored the theories and systematic structures of geomorphologic data mining and acknowledge discovery from dems, ascertained the systematic structures of topographic factors and synthetic topographic acknowledge, as well as systemically summarized mining algorithms from dems. the author pa id more attention also to analyze the principle and algorithm of flow length, curvature, relief, the earth ' s surface incision and gully density. in this research, the elementary constitutes and mining algorithms of regional character acknowledge in the loess plateau were probed

    本研究在廣泛總結前人研究成果與研究經驗的基礎上,利用空間數據掘和地形地貌學的基本理論,以陜北黃高原多地貌類型區為實驗樣區,以1 10000比例尺dem為樣本數據,探討了dem中地形地貌數據掘與知識發現的理論方法和體系結構;確定了宏觀和微觀地形因子、地形綜合特徵知識的體系結構;系統總結了dem基本地形因子的提取演算法,並重點對坡長、曲率、地形的起伏度、切割深度和溝壑密度因子提取的原理與演算法作了深入的分析;提出了黃高原地區區域特徵知識的基本構成及其系統完整、科學可行的掘提取演算法;擴充了arcviewgis軟體中dem空間分析的基本功能;實現了以delphi7 . 0為的地形信息輔助掘系統的設計與開發;完成了對黃高原多地貌類型區(樣區)地形信息空間分異特徵的分析。
  5. Have bore stage car, grab, fork - lift truck, self - propelled to bridge machine, booth shop machine, roller, bulldozer, land leveler, tong carries car of stage of build by laying bricks or stones of line of pump, hydraulic pressure, crane, complete station the construction such as appearance, ride meter, dynamo and detect professional equipment 850 ( set ), technology of average per capita equips twenty - five thousand eight hundred yuan

    擁有鉆孔車、掘機、裝載機、自行式架橋機、攤鋪機、壓路機、推機、地機、砼輸送泵、液壓襯砌車、吊車、全站儀、測震儀、發電機等施工及檢測專業設備850(套) ,人均技術裝備2 . 58萬元。
  6. The works included 24 bored piles of 2. 5 meters in diameter and 55 meters in depth, 500 meters long underground concrete diaphragm wall of 0. 8 meters thick and 25 meters deep, 450 pre - cast concrete pile of 0. 5 meters in diameter, 12 meters deep soil excavation with multi - layer post - tensioning shoring system, reinforced concrete pile caps and basement slabs

    其工程內容包括了24支直徑2 . 5米,深達55米直入巖層的鉆孔樁,周長500米,深度25米,厚度0 . 8米的地下連續混凝墻, 450支直徑0 . 5米預制混凝樁, 12米深開,多層水鋼支撐系統,混凝樁承及地庫底板結構。
  7. With the help of this program, this paper does research on the moved backwards of the slide surface, lengthening the anchor section, the soil nail ' s total force, gets conclusion about relations between the soil nail ' s length and the slope ' s grade, height, soil ' s mechanical parameter ; relations between soil nail ' s total force and coulomb soil pressure. with the help of the large multiuse finite element program ansys, this paper analyzes the soil nailing in one - step ' s slopes, in two - steps " slopes, puts the emphasis on the axis force ' s distributing along the soil nail at each rows, the effect of both the excavating mode and the original slope figure to the axis force of the soil nail, the one another effect between the upper - step slope and the nether - step slope in the soil nail ' s axis force, gets conclusion about the design of soil nail at the first low, different slope body is the same with different excavating mode, the original slope figure has more effect to some than others because of the slope body, the reasonably design of the step width in two - steps slopes, the two - steps excavating and retaining has more virtue than the one - step ' s. through soil pressure analysis this paper does research on the differences and the links between the coulomb soil pressure theory and the rankin ' s, the vertical pressure at the slope surface when the slope surface is inclined and the retaining wall is rough, the soil pressure ' s distributing behind the panel, gets conclusion about the effect of both the slope body inner stability and the slope surface local stability to the soil pressure

    通過分析比較,論證了對數螺旋線型比圓弧形作為邊坡的假設滑裂面具有較多的工程優點,並為此編制了一個採用極限衡法分析釘支護的fortran語言程序,以此作工具對滑裂面的后移、釘錨固段的超長、釘總力的大小等方面作了研究,得出了有關釘的長度與邊坡的坡角、坡高、體力學參數的關系、釘總力與庫侖壓力間的關系等結論;採用大型通用有限元數值分析程序ansys分別對採用釘支護的一階邊坡、二階邊坡進行分析,重點是研究各排釘的軸力分佈規律、開方式及原始邊坡形態對釘的軸力的影響、上下階邊坡在釘軸力方面的相互作用,得出了有關第一排釘的設計問題、不同類型的體應適用於特定的開方式、原始開出的邊坡形態對一些類型坡體的邊坡釘支護有較大的影響而對另外一些影響不大、二階邊坡階寬度的合理確定、二階開及支護比一階時具有較多的工程優點等結論;通過壓力分析對朗肯、庫侖兩種經典壓力理論的區別與聯系、坡面傾斜及墻背有摩擦時的坡面豎向應力分佈、面板背壓力的分佈形態作了研究,得出了邊坡支擋壓力受坡體內部穩定與坡面局部穩定兩個方面的影響、釘支護面板背體中卸荷拱的存在對面板受力有利等結論。
  8. When i had done this, i began to work my way into the rock, and bringing all the earth and stones that i dug down out thro my tent, i laid em up within my fence in the nature of a terras, that so it rais d the ground within about a foot and a half ; and thus i made me a cave just behind my tent, which serv d me like a cellar to my house

    做完這些工作后,我又開始在巖壁上打洞,把出來的石方從帳篷里運到外面,沿籬笆堆成一個,約一英尺高。這樣,帳篷算是我的住房,房后的山洞就成了我的地窖。
分享友人