挖填 的英文怎麼說

中文拼音 [tián]
挖填 英文
excavation and filing
  • : 動詞(用工具或手從物體的表面向里掘取) dig; excavate; scoop
  • : 動詞1. (墊平或塞滿) fill; stuff 2. (補足; 充滿) replenish; supplement; complement 3. (填寫) fill in; write
  1. To reduce earthwork costs, the volume of the fills should be equal to the volume of the cuts.

    為了降低土方工程的費用,方量應等於方量。
  2. As the balancing platform tends to make the barycenter move backward, a more balancing stress distribution under the wall, a higher and steadier wall can be achieved. furthermore, the resupine back of the downward wall not only works reasonably, but also can reduce the amount of excavation and filling obviously. so gravity retaining walls with balancing platform are applied heavily

    衡重式擋土墻因具有衡重臺使墻身重心后移、墻底應力趨于平衡,可提高擋土高度、增強墻體穩定性;且仰斜式下墻不僅受力合理、還可減少開與回量等優點而被大量採用。
  3. Abstract : as lanzhou construction areas extend towards gaolan mountains, baita mountains and the valley regions, the problem of environmental control for the made fill & excavation reconstruction project sites becomes more and more obvious

    黃土改造工程場區的環境條件十分復雜,只注重工程建設而忽視環境治理,將危及建築物和工程場地的長期安全。
  4. The same backfilling materials should be used unless otherwise agreed with the electricity supplier. if in doubt, the contractor must seek advice from clp or hec on the specific requirements for backfilling of excavation including the thickness of the bedding layer, type of materials to be used and method of compaction, etc

    承建商如有任何疑問,必須就完成掘后進行回工作的特定規格,包括墊層厚度、使用物料的種類及壓縮方法等資料,徵詢中華電力有限公司(中電)或香港電燈有限公司(港燈)的意見。
  5. Cut - and - cover method

  6. The cut - and - cover tunnels are approximately 500m long extending from the existing mtr hong kong station

    擬建造的明隧道,約長500米,隧道連接現有地鐵香港站。
  7. Cityu has confirmed that the cut - and - cover method would be the most appropriate method for constructing the tunnels along salisbury road

    城市大學已確定明方式是建造沿梳士巴利道的一段隧道的最適當方法。
  8. The government spokesman said, " in fact, the cut - and - cover method would be more costly, lengthy and difficult for the kcrc contractor, as compared with bored tunnelling

    政府發言人說:事實上,對九鐵公司的承建商來說,明方式比鉆隧道方式更為昂貴,所需時間更長,而且難度更高。
  9. As regards the section of tunnels along salisbury road, it is necessary to construct it by the cut - and - cover method to avoid possible hazards to the adjacent buildings, the existing utilities and the very important mtr tsuen wan line tunnel along nathan road

    至於沿梳士巴利道的一段隧道,則有需要以明方式建造,以避免對毗鄰的建築物、現有的公用設施和沿彌敦道的一段極重要的地鐵荃灣線構成任何潛在的危險。
  10. This is why a special tunnelling machine capable of excavating through both soft ground as well as hard rock was used. without this machine, the tunnelling would have to be done by cut - and - cover method, causing major traffic and environmental disruption. with this tbm, all these impacts can be avoided

    故此選用這臺既可在軟土又可在硬石層運作的隧道鉆機,避免以明的方法開鑿隧道,免卻對交通及環境造成嚴重影響。
  11. Cut - and - fill design

    挖填設計
  12. Cut - and - fill slope

    挖填斜坡
  13. Because of that, engineers need to create the profiles piece by piece, and also, the data within profile drawings, such as cut - and - fill, engineers have to do it manually

    此外,縱斷面圖的各項數據資料,如:現地高程、設計高程、方、方…等資料,也必須一項一項的手動完成。
  14. Simulation and analysis are made for the various excavation schemes for the drift cut - and - fill stoping production in xiaotianjing mine district of heqing manganese ( group ) co. by 3 - d fem and the optimized excavation scheme has played a great role in assuring a safety mine production

    應用三維有限單元法對鶴慶錳業集團公司小天井礦區上向進路分層乾式充采礦過程進行了不同開方案的模擬分析,所優選的開方案對礦山安全生產起到較大作用,模擬結果與生產實際基本一致。
  15. After the users input control tasks in three modes : natural language, electric sheet or flow char, the computer will receive the information of control demands by data mining and knowledge discovery. and then illation is leaded to select the hardware and program the software in the inner of the computer. afterward, control program is transformed in the file format of exiting simulation software by using the simulation interface and is opened in the simulation software

    用戶只需在pc機上以自然語言或繪制控制流程圖、寫表格的方式輸入控制任務,然後在系統內部經過數據掘和知識發現分析得到可用控制要求信息,並自動引導推理求解過程進行硬體選型和生成相應的控製程序,最後利用模擬介面,自動將控製程序轉化為現有的控制模擬軟體的文件格式,並在控制模擬軟體中,從而用戶可以對生成的控制系統進行模擬,檢查設計的正確性。
  16. The power plant was decided to be sited at yahekou in 1972. beginning leveling of the site on aug. 10, 1992, taking 9 months to finish an earthwork with volume of 1. 67 million m3

    1鴨河口電廠1972年選址, 1992年8月10日場地破土平整,歷時9個月,挖填土石方267萬立六米。
  17. Balance cut and fill

    挖填之平衡
  18. Cut and fill design

    挖填設計
  19. The road and its associated cut and fill slopes avoid impacting on traditional burial grounds, fung shui woodlands and the castle peak firing range. this is achieved by placing the road on a 500m long viaduct

    此外,其中路段會建於長500米的高架橋上,使道路及相關的挖填斜坡,不會影響傳統墓地、風水林及青山操炮區。
  20. The major activities involved during the construction stage of the project are cut and fill earthworks, slope works, earth retaining walls, irrigation buffer lake, detention ponds and tanks, sand bunkers and golf course capping and turfing

    2 . 3 . 1在工程項目的施工期內,主要的工程活動包括挖填土方工程斜坡工程護土墻灌溉緩沖湖靜水塘缸沙坑及高爾夫球場的加蓋草皮鋪設。
分享友人