pipe rock 中文意思是什麼

pipe rock 解釋
管巖
  • pipe : n 1 管,導管,筒。2 煙斗,煙袋;一袋煙。3 〈古語〉笛,管樂器;【航海】(水手長的)哨子(聲);〈p...
  • rock : n 1 巖,巖石,磐石,巖壁;卵石;〈常 pl 〉〈美口〉石子兒;暗礁,巖礁。2 〈the R 〉直布羅陀 (Gibr...
  1. If the character of wall rock is finer, it is smaller for suffered force and distortion of tunnel pipe liner structure, contrarily it is bigger

    性態好的圍巖,隧洞襯砌的受力和變形較小,反之則較大。
  2. The factors that probably leads to cracks are put forward based on the analysis, which in turn are : the deformation of surrounding rock and the deformation of concrete volume and the pelter of air temperature and thermal insulation temperature rise and the thickness of liner and cooling pipe

    通過分析得出了導致裂縫的幾種可能原因依次為:混凝土的圍巖變形、自生體積變形、氣溫驟降、絕熱溫升、襯砌厚度和冷卻水管等,為今後類似工程提供理論依據。
  3. In the design, the construction measures such as application of shrinkage - compensating concrete, arrangement of spacing layer between the foundation rock and the bottom slab, adding outside waterproof layer, flexible connection between outlet pipe with side - wall, integerated concrete placement of pump seat with bottom slab and design of reinforcement with application of advanced calculation theory are used according to the characteristics of lager span, larger volume and complex loading conditions of the understructure

    針對下部結構跨度大、體積大、受力復雜的特點,在設計中採取多種措施,包括採用補償收縮混凝土、基巖與底板間設隔離層、增設外防水層、出水管與邊墻採用柔性連接、機座與底板整體澆注、採用先進計算理論指導配筋。
  4. Cement injection of perforating holes in a frozen pipe is a wholly - new technology for consolidating shaft wall rock and stopping water of frozen shafts in coal mines

    凍結管射孔注漿是在對石油輸油井射孔技術和地面注漿技術進行研究的基礎上,開發出的一種用於煤礦凍結井筒圍巖加固和堵水的全新技術。
  5. Abstract : cement injection of perforating holes in a frozen pipe is a wholly - new technology for consolidating shaft wall rock and stopping water of frozen shafts in coal mines

    文摘:凍結管射孔注漿是在對石油輸油井射孔技術和地面注漿技術進行研究的基礎上,開發出的一種用於煤礦凍結井筒圍巖加固和堵水的全新技術。
  6. The technology, which is developed on the basis of perfora ting techniques for oil wells and cement injection techniques, can not shoot thr ough the frozen pipe wall at predetermined ground location using energy - gatheri ng - blasting techniques, but also consolidate shaft wall rock by cement injectio n and filling along the frozen pipe and perforated hole s trajectories, achievi ng leakageproof of shaft walls and reducing vertically - added force

    它利用聚能射孔爆破技術,在預定地層位置將凍結管射穿,同時在地面利用凍結管及射孔彈道對特定地層進行注漿充填加固,既可實現井壁堵漏,又能減少由於地層沉降對井壁的垂直附加力。
  7. Concerning the construction of the shallow cover and the special shallow cover in the tunnel under the special geology conditions, the principle of " to stabilize the slopes with protecting arch ; to strengthen the earth with the pipe - shield support grouting ; to dig a hole shallowly ; to blast slightly ; to use strong supporting structure. " has been adopted to enter the tunnel safely ; in terms of the broken belt, the effective actions such as the pipe - shield support grouting, strengthening the surrounding rock in advance with advanced bolt and steel grids, and so on, are taken to pass the poor conditioned part smoothly

    對于特殊地質中的淺理、特淺埋進洞的施工,堅持「護拱穩定邊仰坡,大管棚注漿加固土體,淺打眼、弱爆破、強支護」的原則,做到安全進洞;對于斷層破碎帶,則採取了管棚注漿,超前錨桿預先加固圍巖並結合鋼格柵支撐等有力措施,順利通過了不良地段。
  8. 1. under the same kind of wall rock and the same condition, displacement of pipe liner is symmetry, for tunnel structure and suffered load are symmetry. as level terra stress is bigger, the maximum of displacement and the first main stress occur in tie - in of pipe liner structure, and its direction is radial and points in hole ; the direction of the third main stress is annular and its maximum occurs in top and bottom hole inner

    1 、同一類圍巖在同一種工況下,由於結構和荷載的對稱性,管片襯砌結構的位移也表現出對稱性,因水平向地應力較大,位移最大值、第一主應力的最大值發生在管片襯砌結構的接頭處,方向為徑向指向洞內;第三主應力的方向為環向,較大值發生在洞頂和洞底內側。
  9. 3. under different kinds of wall rock and the same condition, from ii iii v kinds of wall rock, and conditions of construction period and operation period, it gradually increases that the maximum of displacement and the first main stress third main stress of pipe liner structure

    3 、不同種類圍巖在相同的工況下,從、 、類圍巖看,不論是施工期還是運行期,管片襯砌結構的位移的最大值和第一主應力、第三主應力最大值都逐漸增大。
  10. 2. under the same kind of wall rock and different conditions, the maximum of displacement and the third main stress of pipe liner structure in construction period is bigger than these of operation period, and the maximum of the first main stress of pipe liner structure in construction period is smaller than these of operation period

    2 、同一類圍巖在不同工況下,施工期管片襯砌結構位移的最大值、第三主應力最大值比運行期要大,施工期的管片襯砌結構的第一主應力最大值比運行期要小。
  11. In this paper, it is studied and analyzed characteristic of stress, distortion etc. of pipe liner structure combining dahuofang transport water tunnel practice project, tunnel boring machine construction, and it is considered that affects internal force of pipe liner for early stress of underground structure and digging load. in nonlinear finite element calculation model, folium cells have been simulated among pipe liner and pipe liner and wall rock. under varies load condition, it has educed that changing rule of stress, distortion and load characteristic pipe liner in kinds of wall rock tunnel by analysis and calculation

    本文結合實際工程,分析研究了大夥房水庫輸水隧道工程在採用掘進機施工方法的情況下,利用管片襯砌的結構應力、變形等受力特性,考慮地下結構初始應力和開挖荷載對襯砌內力的影響,採用薄層單元模擬襯砌管片之間、襯砌管片與圍巖之間的非線性有限元計算模型,通過分析計算得出不同荷載工況下各類典型圍巖段隧道襯砌管片受力特徵、應力和位移變化規律。
  12. Step 6 : after complete the grouting and curing work between all the installation work in the liner ( including process piping, pipe support, etc. ) & liner and rock bed, complete the installation work of top elliptic head of liner using 35 / 50 ton hyd - crane and 25 ton truck crane

    第六步:待襯管內所有的安裝工作(包括工藝配管、管道支架等)及襯管與巖床間的灌漿、養護工作完成後,用35 / 50噸液壓起重機和25噸汽車起重機完成襯管頂部封頭的安裝工作。
  13. The experimental method of the model test with 1 : 6 scale based on the work mechanism of bearing of steel y - pipe strengthened inside with crescent rib in combination with surrounding rock mass simulated by composite materials is adopted and the regularity of their participant capacity to bear inner water pressure is analyzed in this paper

    摘要本文結合實際工程採用幾何比尺為1 : 6的物理模型試驗方法,用不同材料分層組合模擬圍巖,對水電站內加強月牙肋鋼岔管與圍巖聯合承載的工作機理、圍巖分擔內水壓力的規律進行分析。
  14. On the basis of analyzing the rock mechanics, the bit working circumstance and property in the bottom hole of 6000m deep well, and making use of the former equipment such as a derrick, platforms etc, the paper demonstrates that the research and design of the mechanical device have been established including the high pressure simulating well bore, the high pressure connector between the static well bore and the rotating drill pipe, the high pressure simulating system of circulating fluid and the high pressure desander etc. the produce, control and dynamic analysis of the bottom hole four - dimensional pressure ( over burden, confined, pore and column pressure ) have been studied

    本文在對井底巖石的受力狀態以及鉆頭的工作環境和特性加以分析的基礎上,藉助原有的井架、平臺等設備,研究設計了模擬6000米井底壓力壞境的高壓模擬井筒、鉆柱高壓轉聯器、鉆井液高壓模擬系統以及高壓除砂器等機械裝置,並研究了井底四維模擬壓力(上覆壓、圍壓、孔隙壓和液柱壓)的產生、控制及其控制的建模與模擬,從而實現井深至6000米的四維井底壓力環境的模擬。
  15. In view of very large scale of y - pipes of this project, the design of combined bearing of y - pipe and surrounding rock is adopted to decrease the difficulty of fabrication and erection

    摘要西龍抽水蓄能電站岔管規模遠超過國內已建工程,為降低製作、安裝難度,考慮岔管與圍巖聯合受力設計。
  16. The mechanics character of wall rock distinctly affects suffered force and distortion of pipe liner structure

    圍巖的力學性質對管片襯砌結構的受力和變形有較大的影響。
  17. This test provides the important bases for determining the design parameters and studying the combined bearing law of the y - pipe and surrounding rock modeling under actual bearing conditions and the construction technology of y - pipe tests of site structural model

    在大量結構分析基礎上,通過現場結構模型試驗對埋藏式岔管實際受力狀態和施工工藝的模擬,為設計參數取值、岔管與圍巖聯合受力規律研究,提供重要的科學依據。
  18. In chapter two, the rock mechanics and the bit working circumstance in the bottom hole of 6000m deep well have been discussed. on the basis of which the high pressure simulating well bore and the high pressure connector between the static well bore and rotating drill pipe have been designed

    第二章分析探討了井底巖石的受力狀態以及鉆頭的工作環境,並依此研究分析了建立該模擬壓力環境的機械裝置?高壓模擬井筒和鉆柱高壓轉聯器。
分享友人